FREE BOOKS

Author's List




PREV.   NEXT  
|<   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42  
43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   >>   >|  
els _A_ and _C_ were originally fitted with fixed hoods and fixed extensions to the floors, as shown in Fig. 2, Plate LXV. A full description of the shields will be found in Mr. Japp's paper. The shields in each pair of tunnels were advanced through the solid rock section about abreast of each other, until test holes from the faces indicated soft ground within a few feet. As the distance between the sides of the two tunnels was only 14 ft., it was thought best to let Tunnels _B_ and _D_ gain a lead of about 100 ft. before Tunnels _A_ and _C_ opened out into soft ground, in order that a blow from one tunnel might not extend to the other. Work in Tunnel _C_ was shut down on December 23d, 1905, after exposing sand to a depth of 3 ft. at the top, and it remained closed for seven weeks. Work in Tunnel _A_ was suspended on September 29th, 1905. By the time Tunnel _B_ had made the required advance, it, together with Tunnels _C_ and _D_, was overtaxing the capacities of the compressor plant. Only a little work was done in Tunnel _C_ until July, 1906, and work in Tunnel _A_ was not resumed until October 22d, 1906. TUNNELS DRIVEN WESTWARD FROM LONG ISLAND CITY. _Materials and Inception of the Work._--The materials met in Tunnel A are typical of all four tunnels. From the Long Island shafts westward, in succession, there were 124 ft. of all-rock section, 125 ft. of part rock and part earth section, 22 ft. of all-rock section, 56 ft. of part rock and part earth section, 387 ft. of all-rock section, 70 ft. of part earth and part rock section, and 1,333 ft. of all-earth section. [Illustration: PLATE LXVII] The materials passed through are indicated on Plate XIII. The rock was similar to that of the Blackwell's Island Reef, and was likewise covered by a layer of sand and boulders. The remainder of the soft ground was divided into three classes. The first was a very fine red sand, which occurred in a layer varying in thickness from 6 ft. to at least 15 ft. It may have been much deeper above the tunnel. It is the quicksand usually encountered in all deep foundations in New York City. The following is the result of the sifting test of this sand: Held on No. 30 sieve 0.6% Passed No. 30, " " No. 40 " 0.4% " No. 40, " " No. 50 " 0.7% " No. 50, " " No. 60 " 2.4% " No. 60, " " No. 80 " 14.9% " No. 80, " " No. 100 " 54.0% " No
PREV.   NEXT  
|<   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42  
43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   >>   >|  



Top keywords:

section

 

Tunnel

 

Tunnels

 

tunnels

 
ground
 

materials

 

Island

 
tunnel
 

shields

 
Illustration

likewise

 

Blackwell

 
similar
 

passed

 

typical

 
Materials
 

Inception

 
shafts
 

covered

 

westward


succession

 

remainder

 

quicksand

 
foundations
 

deeper

 

thickness

 

result

 

classes

 

divided

 

Passed


boulders

 

encountered

 

occurred

 

varying

 

sifting

 

distance

 
opened
 
thought
 
abreast
 

floors


extensions
 

originally

 

fitted

 

advanced

 

description

 

capacities

 

compressor

 

overtaxing

 

required

 

advance