FREE BOOKS

Author's List




PREV.   NEXT  
|<   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73  
74   75   76   77   78   >>  
POLT AND TWISTED STEEL RODS.] In Tunnel _B_, after passing out from under the bulkhead line, in April, 1906, the loss of air became very great, and blow-outs were of almost daily occurrence until the end of June. At the time of the blows the pressure in the tunnel would drop from 2 to 8 lb., and it generally took some hours to raise the pressure to what it was before the blow. During that time regular operations were interrupted. In the latter part of June a permit was obtained allowing the clay blanket to be increased in thickness up to a depth of water of 27 ft. at mean low tide. The additional blanket was deposited during the latter part of June and early in July, and almost entirely stopped the blows. By the end of the month the natural clay, previously described, formed the greater portion of the face, and, from that time forward, played an important part in reducing the quantity of air required. During April and the early part of May the work was under the ferry racks of the Long Island Railroad. The blanket had to be placed by dumping the clay from wheel-barrows through holes in the decking. In Tunnel _A_ a bottom heading had been driven 23 ft. in advance of the face at the time work was stopped at the end of 1905. During the ten months of inactivity the seams in the rock above opened. The rock surface was only from 2 to 4 ft. below the top of the cutting edge for a distance of about 60 ft. Over the rock there were large boulders embedded in sharp sand. It was an exceedingly difficult operation to remove the boulders and place the polings without starting a run. The open seams over the bottom heading also frequently caused trouble, as there were numerous slides of rock from the face which broke up the breasting and allowed the soft material from above to run into the shield. There were two runs of from 50 to 75 cu. yd. and many smaller ones. [Footnote D: The lead of the shield is the angular divergence of its axis from the axis of the tunnel and, in this tunnel, was measured as the offset in 23 ft. It was called + when the shield was pointed upward from grade, and - when pointed downward.] GUIDING THE SHIELDS. Little difficulty was experienced at any time in driving the shield close to the desired line, but it was much harder to keep it on grade. In rock section, where the cradle could be set far enough in advance to become hard before the shield was shoved over it, there was no trouble whatever.
PREV.   NEXT  
|<   49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73  
74   75   76   77   78   >>  



Top keywords:
shield
 

tunnel

 

blanket

 

During

 

boulders

 

pointed

 

trouble

 
bottom
 

heading

 
advance

stopped

 

pressure

 

Tunnel

 

cradle

 

polings

 
starting
 

frequently

 
slides
 

breasting

 

numerous


section

 
caused
 

shoved

 

distance

 

embedded

 

difficult

 

operation

 
exceedingly
 

remove

 

material


driving
 

desired

 
angular
 

divergence

 

measured

 

offset

 

SHIELDS

 

GUIDING

 

upward

 

Little


difficulty

 

experienced

 

called

 
downward
 
harder
 

Footnote

 
smaller
 

allowed

 

regular

 

operations