FREE BOOKS

Author's List




PREV.   NEXT  
|<   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  
ds outside the iron lining of the sump and the pump chamber were filled as completely as possible with concrete, and then thoroughly grouted. Finally, the concrete lining was put in place inside of the iron. As shown by Fig. 3, the excavation of these chambers left a considerable portion of the iron lining of the tunnels temporarily unsupported on the lower inner quarter. To guard against distortion, a system of diagonals and struts was placed as shown. The floor of the pump chamber was water-proofed with felt and pitch in a manner similar to that described for the caissons at Long Island City. It was not possible to make the felt stick to the vertical walls with soft pitch, which was the only kind that could be used in compressed air, and, therefore, the surfaces were water-proofed by a wall of asphalt brick laid in pitch melting at 60 deg. Fahr. Forms were erected on the neat line, and the space to the rock was filled with concrete making a so-called sand-wall similar to that commonly used for water-proofing with felt and pitch. The bricks were then laid to a height of four or five courses. The joints were filled with pitch instead of mortar. Sheets of tin were then placed against the face of the wall and braced from the concrete forms. As much pitch as possible was then slushed between the brick and the sand-wall, after which the concrete in the main wall was filled up to the top of the water-proofing course. The tin was then withdrawn and the operation repeated. This method was slow and expensive, but gave good results. Ordinary pitch could not be used on account of the fumes, which are particularly objectionable in compressed air. The 60 deg. pitch was slightly heated in the open air before using. [Illustration: FIG. 3.] The sump and pump chamber on Tunnels _C_ and _D_ differed from the one described only in minor details; but, being wholly constructed in rock, presented fewer difficulties and permitted a complete envelope of water-proofing to be placed in the top. CONCRETE LINING. The placing of concrete inside the iron tube was done by an organization entirely separate from the tunneling force. A mixing plant was placed in each of the five shafts. The stone and sand bins discharged directly into mixers below, which, in turn, discharged into steel side-dump concrete cars. All concrete was placed in normal air. The first step, after the iron lining was scraped clean and washed down and all leaks w
PREV.   NEXT  
|<   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

concrete

 

lining

 
filled
 

proofing

 

chamber

 

proofed

 

similar

 

compressed

 

discharged

 
inside

details
 

wholly

 

method

 
expensive
 
presented
 

results

 

constructed

 
differed
 

heated

 
slightly

Tunnels

 
Illustration
 
objectionable
 

Ordinary

 

account

 

tunneling

 
directly
 

mixers

 

normal

 
washed

scraped
 

placing

 

LINING

 

CONCRETE

 

permitted

 

complete

 

envelope

 

organization

 

shafts

 
mixing

separate
 
difficulties
 

called

 

system

 

diagonals

 
struts
 

distortion

 

quarter

 

manner

 

Island