FREE BOOKS

Author's List




PREV.   NEXT  
|<   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48  
49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   >>   >|  
held tightly against the planking by the pressure of the floor jacks. While shoving, the pressure on the floor jacks was gradually released, allowing the floors to slide back into the shield and still afford support to the face. The extensions also afforded convenient working platforms. They were subject to severe bending strains while the shield was being shoved, however, and the cast-iron rams were frequently broken or jammed. The extensions did not last beyond the edge of the ledge at Manhattan, nor more than about half through the rock work at Long Island City. The fixed extensions originally placed on Shields _A_ and _C_ at Manhattan were not substantial enough, and lasted only a few days. Wherever the rock face was sufficiently sound and high, a bottom heading was driven some 20 or 30 ft. in advance of the shield. The heading was driven and the cradle placed independently of the face of the soft ground above, and in the manner described for all-rock sections. The remainder of the rock face was removed by firing top and side rounds into the bottom heading after the soft ground had been excavated. Great care had to be taken in firing in order not to disturb the timber work or break the rock away from under the breast boards. If either occurred, a serious run was likely to follow. The bottom-heading method is shown by Figs. 1, 2, and 3, Plate LXVIII, and the breasting and poling by Fig. 2, Plate LXX. In the early part of the work, where a bottom heading was impracticable, the soft ground was first excavated as described above, and the rock was drilled by machines mounted on tripods, and fired as a bench. By this plan no drilling could be done until the soft ground was removed. This is called the rock-bench method. Later the rock-cut method was devised. Drills were set up on columns in the bottom compartments of the shield, and the face was drilled while work was in progress on the soft ground above. The drilling was done either for a horizontal or vertical cut and side and top rounds. The drillers were protected while at work by platforms of timber built out from the floors of the compartments above. This plan, while probably not quite as economical of explosives, saved nearly all the delay due to drilling the bench. [Illustration: PLATE LXX, FIG. 1.--SMALL SHAFT SUNK TO ROCK.] [Illustration: PLATE LXX, FIG. 2.--BREASTING AND POLING IN FRONT OF SHIELD.] [Illustration: PLATE LXX, FIG. 3.--SHUTTERS ON FRO
PREV.   NEXT  
|<   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48  
49   50   51   52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   >>   >|  



Top keywords:

heading

 

ground

 

bottom

 
shield
 

method

 
extensions
 

drilling

 

Illustration

 

removed

 
driven

firing

 

drilled

 

compartments

 

rounds

 

excavated

 

Manhattan

 

timber

 
floors
 
pressure
 
platforms

gradually

 

mounted

 
tripods
 

called

 

machines

 

shoving

 

allowing

 
LXVIII
 

breasting

 

poling


impracticable

 

devised

 

released

 

Drills

 

tightly

 

BREASTING

 

SHUTTERS

 
SHIELD
 

POLING

 
horizontal

vertical

 

drillers

 

progress

 

planking

 

columns

 

protected

 

explosives

 

economical

 

afford

 

follow