All rock |129 | 373 | 2.89 | |
| | | | |
Earth and rock| 77 | 190 | 2.47 | |
| | | | |
All earth |164 |1,275.6 | 7.78 | |
--------------+------+--------+--------+--------------------------------------+
LINE A, MANHATTAN.
--------------+-----------------+-------------------+-------------------------+
| | Station: | Date: |
| |---------+---------+------------+------------+
| | | | | |
Material. | Method. | From | To | From | To |
--------------+-----------------+---------+---------+------------+------------+
{|Top heading |108+43 |107+74 |July 20, '05|Aug. 3, '05|
Rock {|Top lift of bench|108+43 |107+74 |Aug. 8, '05|Aug. 23, '05|
{|Bottom lift of |108+43 |107+74 |Aug. 30, '05|Sept 27, '05|
{| bench | | | | |
| | | | | |
Rock {|Bottom heading |107+74 |107+21 |Sept 27, '05|Oct. 23, '05|
{|Bottom heading |107+74 |107+21 |Nov. 30, '05|Dec. 29, '05|
| | | | | |
Mixed |Bottom heading |107+21 |106+99 |Oct. 26, '06|Nov. 20, '06|
| | | | | |
Mixed |Rock bench |106+99 |106+34 |Nov. 20, '06|Jan. 13, '07|
| | | | | |
Earth |Poling and |106+34 | 99+11 |Jan. 13, '07|Apr. 17, '07|
| breasting | | | | |
| | | | | |
Mixed |Rock cut | 99+11 | 93+96 |Apr. 17, '07|Oct. 24, '07|
| | | | | |
Rock |Bottom heading | 93+96 | 93+58 |Oct. 24, '07|Nov. 14, '07|
| |
|