FREE BOOKS

Author's List




PREV.   NEXT  
|<   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  
the tunnel. Many of these had been reinforced by the use of _XX_, _YY_, and steel segments placed adjacent to the break in the following rings. After the meeting of the shields, the postponed replacement of the broken segments was taken up. The pressure was raised sufficiently to dry thoroughly the sand outside the segments, which were drilled and broken out usually in quarters as shown on Fig. 1, Plate LXXIII. A steel segment was then inserted in the ring and drawn into place by turnbuckles. The application of the draw-jack, with a pull of about 30 tons to each end successively, brought the plate to a firm bearing on the radial joints at the ends. Where the broken plate was isolated and was reinforced by steel or extra heavy segments in the adjacent ring, the crack, if slight, was simply caulked to insure water-tightness. If, however, the crack was opened or extended to the web of the plate, the cross-flanges were tied together by a 1-1/2-in. by 7-ft. bolt, inserted through the bolt holes nearest the broken flange. The long bolt acted in the nature of a bow string, and was provided at its ends with two nuts set on opposite sides of the cross-joints to replace the standard bolts removed for its insertion. Fig. 4, Plate LXXIII shows one of these bolts in place. In addition, all broken plates remaining in the tunnel were reinforced with 1-in. twisted-steel rods in the concrete lining, also shown in Fig. 4, Plate LXXIII. _Special Construction at River Shield Junctions._--Dismantling the shields was started as soon as they came to rest in their final position with the cutting edges together. The plans contemplated their entire removal, with the exception of the cylindrical skins and cast-steel cutting edges. Inside the former the standard tunnel lining was erected to within 4 ft. of the heels of the cutting edges. Spanning the latter, and forming the continuous metal tunnel lining, the special construction shown by Fig. 2 was built. This consisted of a 1-1/4 in. rolled-steel ring, 7 ft. long, erected inside the cutting edges, with an annular clearance of 1 in., and two special cast-iron rings shaped to connect the rolled-steel ring with the normal lining. One flange of the special cast-iron rings was of the standard type, the other was returned 9 in. in the form of a ring, the inside diameter of which was the same as the outside diameter of the rolled-steel ring to which it was bolted. The space between the standard
PREV.   NEXT  
|<   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

broken

 

standard

 
tunnel
 

lining

 

cutting

 

segments

 

reinforced

 

rolled

 

special

 
LXXIII

joints
 

erected

 

inside

 
diameter
 
flange
 

shields

 

adjacent

 
inserted
 

position

 
exception

cylindrical

 
removal
 
entire
 

contemplated

 

Junctions

 

remaining

 
twisted
 

plates

 

addition

 
concrete

Shield
 

Dismantling

 

Construction

 

Special

 

started

 

normal

 

connect

 

clearance

 

shaped

 
returned

bolted
 
annular
 

Spanning

 

forming

 

continuous

 
consisted
 

construction

 

Inside

 

insertion

 

drilled