FREE BOOKS

Author's List




PREV.   NEXT  
|<   68   69   70   71   72   73   74   75   76   77   78   >>  
where a space of about 18 in. was left. When the lagging had reached the upper hanger-bolts, they were removed, which left only the two bottom bolts fixed in the concrete. Most of these were unscrewed from the eye and saved, as tin sleeves were placed around them before concreting. Two cast-iron eyes were lost for every 5 ft. of tunnel. To place the key concrete, a stage was set up in the middle of the floor, and, beginning at one end, about 2 ft. of block lagging was placed. Over this, concrete was packed, filling the key as completely as possible. This was done partly by shoveling and using a short rammer, and partly by packing with the hands by the workmen, who wore rubber gloves for the purpose. Another 2 ft. of lagging was then placed, and the operation was repeated, and thus working backward, foot by foot, the key was completed. This is the usual way of keying a concrete arch, but in this case the difficulty was increased by the flanges of the iron lining. It was practically impossible to fill all parts of the pockets formed by these flanges. To meet this difficulty, provision was made for grouting any unfilled space. As the concrete was being put in, tin pipes were placed with their tops nearly touching the iron lining, and their bottoms resting on the lagging. Each pocket was intended to have two of these pipes, one to grout through and the other to act as a vent for the escape of air. Each center key ring had six pipes, and each side key had eight. The bottoms of the pipes were held by a single nail driven half way into the lagging. This served to keep the pipes in position and to locate them after the lagging was taken down. The cost of labor in the tunnels directly chargeable to concrete was $1.80 per cu. yd. The top charges, exclusive of the cost of materials (cement, sand, and stone), amounted to $3.92. ELECTRIC CONDUITS. In one bench wall of each tunnel there were fifteen openings for power cables and in the other, between the river shafts, there were forty openings for telephone, telegraph, and signal cables. East of the Long Island shaft, the number of the latter was reduced to twenty-four. The telephone ducts were all of the four-way type. The specifications required that the power ducts should have an opening of not less than 3-1/2 in., nor more than 3-7/8 in., and that after laying they should pass a 4-ft. mandrel, 3-3/8 in. at the leading end and 2-5/8 in. at the other. The outside dimension
PREV.   NEXT  
|<   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

concrete

 

lagging

 
difficulty
 

cables

 

tunnel

 

partly

 

lining

 

telephone

 

openings

 
flanges

bottoms
 

directly

 

tunnels

 
chargeable
 
single
 

center

 

escape

 
position
 

locate

 
served

driven

 
specifications
 
required
 

opening

 

twenty

 

number

 
reduced
 

mandrel

 

leading

 
dimension

laying
 

Island

 

amounted

 

ELECTRIC

 

CONDUITS

 

charges

 

exclusive

 

materials

 

cement

 
telegraph

signal
 
shafts
 

fifteen

 

pockets

 

middle

 
beginning
 

packed

 

rammer

 

packing

 

shoveling