FREE BOOKS

Author's List




PREV.   NEXT  
|<   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  
ere stopped, was the placing of biats, marked _B_ on Plate LXXIV. These were made up of a 6 by 12-in. yellow pine timber, 17 ft. long, with two short lengths of the same size spliced to its ends by pieces of 12-in. channels, 3 ft. 9 in. long, clamped upon the sides. These biats were placed every 5 ft. along the tunnel in rings having side keys. Next, a floor, 13 ft. wide, was laid on the biats and two tracks, of 30-in. gauge and 6-1/2-ft. centers, were laid upon the floor. There were three stages in the concreting. Fig. 2, Plate LXXIV, shows the concrete in place at the end of the first, and Fig. 3, Plate LXXIV, at the end of the second stage. The complete arch above the bench walls was done in the last operation. Two 3 by 10-in. soldiers (_SS_ in Figs. 1 and 2, Plate LXXIV) were fastened to each biat and braced across by two horizontal and two diagonal braces. To each pair of soldiers a floor template, _T_, was then nailed. The form for the center drain was then suspended as shown in Fig. 1, Plate LXXIV. Three pieces of shuttering, _FFF_, 20 ft. long, were then nailed to the bottom of the soldiers. One is all that would have been needed for the first concrete placed, but it was easier to place them at this stage than later, when there was less room. Three rough shutters were also nailed to the curved portion for the floor template. Opposite each biat, a bracket, _bb_, was then nailed, which carries a set of rough boards which formed the risers for the duct steps. Everything was then ready for concreting except that, where refuge niches occurred, a form for the portion of the niche below the seat was nailed to the shuttering. This form is shown at _R_ in Fig. 1, Plate LXXIV. [Illustration: PLATE LXXIV] The concrete was dumped down on each side from side-dump cars standing on the track, and, falling between the risers for the duct steps, ran or was shoveled under the forms and down into the bottom. The horizontal surface on each side the center drain was smoothed off with a shovel. The workmen became very skillful at this, and got a fairly smooth surface. This concrete was usually placed in lengths of 45 or 60 ft. After setting for about 24 hours, the brackets, _bb_, were removed, together with the shuttering on the steps. The triangular pieces, _t_ in Fig. 1, Plate LXXIV, were not removed until later. Instead, a board was laid upon this lower step on which the duct layers could work. This and the triangular piece
PREV.   NEXT  
|<   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

nailed

 

concrete

 
shuttering
 

soldiers

 

pieces

 

bottom

 

surface

 

concreting

 

center

 
lengths

template
 

horizontal

 

triangular

 
risers
 
portion
 

removed

 

Illustration

 
dumped
 

refuge

 
boards

formed

 
carries
 
bracket
 

curved

 

Opposite

 

placing

 
stopped
 

niches

 

occurred

 
Everything

brackets
 

setting

 

layers

 

Instead

 

smooth

 

shoveled

 

falling

 

standing

 

smoothed

 
skillful

fairly
 
shovel
 

workmen

 

stages

 

centers

 
tracks
 

timber

 

complete

 

yellow

 

spliced