FREE BOOKS

Author's List




PREV.   NEXT  
|<   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  
e leakage, leaving 0.0032 cu. ft. per sec. or 0.00000081 cu. ft. per sec. per lin. ft. of tunnel to be accounted for as general seepage distributed over the whole length. It was not feasible to stop every leak in the tunnel, most of which were indicated simply by damp spots on the concrete; a rather simple method was devised, however, for stopping the leaks at the eight or ten places in each tunnel where water dripped from the arch or flowed down the face of the concrete. The worst leak in any tunnel flowed about 0.0023 cu. ft. per sec. To stop these leaks, rows of 1-in. holes, at about 4-in. centers, were drilled with jap drills through the concrete to the flange of the iron. These rows were from 3 to 18 ft. long, extending 1 ft. or more beyond the limits of the leak. The bottoms of the holes were directly on the caulking groove and the pounding of the drill usually drove the caulking back, so that the leak became dry or nearly so after the holes were drilled. If left alone the leaks would gradually break out again in a few hours or a few days and flow more water than before. They were allowed to do this, however, in only a few cases as experiments. After the holes were drilled, the bottom 4 in. next the flange was filled with soft neat cement mortar. Immediately on top of this was placed two plugs of neat cement about 2-1/2 in. long, which were 5 or 6 hours old and rather hard. Each was tamped in with a round caulking tool of the size of the hole driven with a sledge hammer. On top of this were driven in the same way two more plugs of neat cement of the same size, which were hard set. These broke up under the blows of the hammer, and caulked the hole tight. When finished, the tamping tool would ring as though it was in solid rock. Great pressure was exerted on the plastic mortar in the bottom of the hole, which resulted in the re-caulking of the joint of the iron. No further measurable leakage developed in the repaired cracks, during a period of four months, and the total leakage has been reduced to about 0.002 cu. ft. per sec. in each tunnel, an average of 0.00000051 cu. ft. per sec. per lin. ft. SUMP AND PUMP CHAMBERS. To take care of the drainage of the tunnels, a sump with a pump chamber above it was provided for each pair of tunnels. The sumps were really short tunnels underneath the main ones and extending approximately between the center lines of the latter. They were 10 ft. 9-1/2 in. in outside diamete
PREV.   NEXT  
|<   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

tunnel

 

caulking

 

tunnels

 

cement

 

leakage

 

drilled

 

concrete

 

flange

 
extending
 

mortar


bottom

 

driven

 

hammer

 

flowed

 

diamete

 

provided

 

finished

 
tamping
 

caulked

 

center


tamped
 

approximately

 

sledge

 

underneath

 

period

 

CHAMBERS

 

cracks

 

00000051

 

average

 

reduced


months

 

repaired

 

developed

 
exerted
 

plastic

 
resulted
 

pressure

 

drainage

 

measurable

 

chamber


gradually

 
places
 
stopping
 
devised
 

simple

 

method

 
dripped
 

centers

 

accounted

 

general