FREE BOOKS

Author's List




PREV.   NEXT  
|<   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  
r and 44 ft. long. The water drops directly from the drains in the center lines of the tunnels into the sumps. Above the sumps and between the tunnels, a pump chamber 19 ft. 5 in. long was built. Above the end of the latter, opposite the sump, a cross-passage was constructed between the bench walls of the two tunnels. This passage gives access from either tunnel through an opening in the floor to the pump chamber and through the latter to the sump. From the preliminary borings it was thought that the sumps were located so that the entire construction would be in rock. This proved to be the case on Tunnels _C_ and _D_, but not on Tunnels _A_ and _B_. The position of the rock surface in the latter is shown by Fig. 3. After the excavation was completed in Tunnel _B_, January 1st, 1908, the plates were removed from the side of the tunnel at the cross-passage, and a drift was driven through the earth above the rock surface across to the lining of Tunnel _A_. The heading was timbered as shown by Fig. 3. There was practically no loss of air from the drift, but the clay blanket had been removed from over this locality and the situation caused some anxiety. In order to make the heading as secure as possible, the 24-in. I-beams, shown on Fig. 3, were attached to the lining of the two tunnels. The beams formed a support for the permanent concrete roof arch of the passage, which was placed at once. At the same time plates were removed from the bottom in Tunnel _B_ over the site of the sump, and a heading was started on the line of the sump toward Tunnel _A_. As soon as the heading had been driven beyond the center line of the pump chamber, a bottom heading was driven from a break-up westward in the pump chamber and a connection was made with the cross-passage. The iron lining of the pump chamber was next placed, from the cross-passage eastward. The soft ground was excavated directly in advance of the lining, and the ground was supported by polings in much the same manner as described for shield work. On account of bad ground and seams of sand encountered in the rock below the level of the cross-beams, the entire west wall of the pump chamber was placed before enlarging the sump to full size. This was also judicious, in order to support as far as possible the iron lining of the tunnels. The sump was then excavated to full size. The iron lining of the sump and the east wall of the pump chamber were placed as soon as possible. The voi
PREV.   NEXT  
|<   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

chamber

 

lining

 
passage
 

tunnels

 

heading

 

Tunnel

 

ground

 

removed

 

driven

 
center

entire
 

Tunnels

 

bottom

 
directly
 
surface
 

plates

 

tunnel

 
support
 

excavated

 
westward

concrete

 
permanent
 
formed
 

attached

 

started

 

encountered

 
enlarging
 

judicious

 

account

 
eastward

advance
 

supported

 

shield

 

manner

 

polings

 

connection

 

locality

 

proved

 

construction

 
position

located
 
constructed
 

access

 

opening

 

thought

 
borings
 

preliminary

 

opposite

 

excavation

 

blanket