FREE BOOKS

Author's List




PREV.   NEXT  
|<   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  
ling and quick setting in the dry sand at that point then became of value. The use of dry lime in the face, where the escaping air would carry it into the voids of the sand and choke them, was much more promptly efficacious in checking the loss. With the exception of the English lime, all grout was mixed 1 to 1 with sand in a Cockburn continuous-stirring machine operated by a 3-cylinder air engine. The grout machine was placed on the lower floor of the trailing platform shown on Plate LXXII, while the materials were placed on the upper platform, and, together with the water, were fed into the machine through a hole in the upper floor. The sand was bagged in the yard, and the cars on which the materials were sent into the tunnels were lifted by an elevator to the level of the upper floor of the trailing platform before unloading. Great difficulty was experienced in preventing the waste of the fluid grout ahead of the shield and into the tail through the space between it and the iron lining. In a full soft ground section, the first condition did not usually arise. In the full-rock sections the most efficient method of checking the waste was found to be the construction of dams or bulkheads outside the lining between it and the rock surface. For this purpose, at intervals of about 30 ft., the leading ring and the upper half of the preceding one were disconnected and pulled forward sufficiently to give access to the exterior. A rough dam of rubble, or bags of mortar or clay, was then constructed outside the iron, and the rings were shoved back and connected up. In sections containing both rock and soft ground, grout dams were built at the cutting edge at intervals, and were carried up as high as circumstances permitted. The annular space at the tail of the shield was at all times supposed to be packed tight with clay and empty bags, but the pugging was difficult to maintain against the pressure of the grout. For a time, 1/2-in. segmental steel plates, slipped down between the jackets and the iron, were used to retain the pugging, but their displacement resulted in a number of broken flanges, and their use was abandoned. In their place, 2-in. segmental plates attached to the jack heads were substituted with more satisfactory results. Notwithstanding these devices, the waste of grout at the tail was very great. The soft ground material on various portions of the work acted very differently. The clay and "bull's liver"
PREV.   NEXT  
|<   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>  



Top keywords:

machine

 

platform

 
ground
 

trailing

 

intervals

 

plates

 

shield

 

lining

 

segmental

 
pugging

sections
 

materials

 

checking

 
forward
 
connected
 

shoved

 

sufficiently

 
disconnected
 

devices

 
material

portions

 
pulled
 
rubble
 

exterior

 

access

 

differently

 
constructed
 

mortar

 

satisfactory

 
abandoned

attached
 

pressure

 

flanges

 

slipped

 

jackets

 

displacement

 

resulted

 

number

 

broken

 
maintain

substituted
 
circumstances
 

carried

 

results

 

retain

 
cutting
 

permitted

 

annular

 

difficult

 

packed