FREE BOOKS

Author's List




PREV.   NEXT  
|<   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51  
52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   >>   >|  
was attached to each. The method of working in soft ground from Long Island City is illustrated by Plate LXXII. The full lines at the face of the shield show the position of the earth before a shove of the shield, and the dotted lines show the same after the shove. The face was mined out to the front of the hood and breasted down to a little below the floor of the top pockets of the shield. In the middle pocket the earth was allowed to take its natural slope back on the floor. Toward the rear of the bottom pockets it was held by stop-planks. The air pressure was always about equal to the hydrostatic head at the middle of the shield, so that the face in the upper and middle pockets was dry. In the lower pockets it was wet, and flowed under the pressure of shoving the shield. By this method 4,195 lin. ft. of tunnel was excavated by the four Long Island shields in 120 days, from November 1st, 1907, to March 1st, 1908. This was an average of 8.74 ft. per day per shield. The rate of progress, the nature of the materials, and the methods adopted are shown in Table 2. _Preparations for Junction of Shields._--As previously mentioned, the Manhattan shields were stopped at the edge of the reef. Before making the final shove of those shields, special polings were placed with unusual care. The excavation was bell-shaped to receive the Long Island shields. The arrangement of the polings is shown by Figs. 4 and 5, Plate LXXI. After the shields were shoved into final position, as shown at the right in Fig. 5, the rear end of the polings rested over the cutting edge and allowed room for the removal of the hood. After the latter had been accomplished, the temporary bulkheads of concrete and clay bags were built as a precaution against blows when the shields were close together. An 8-in. pipe was then driven forward through the bulkhead for distances varying from 30 to 100 ft., in order to check the alignment and grade between the two workings before the shields were actually shoved together. The errors in the surveys were negligible, but here, as elsewhere, the shields were not exactly in the desired position, and it took careful handling to bring the cutting edges together. The Long Island shields were driven to meet those from Manhattan. TABLE 2.--RATE OF PROGRESS, NATURE OF MATERIALS, AND METHODS ADOPTED IN CONSTRUCTION OF EAST RIVER TUNNELS. LINE A, LONG ISLAND. --------------+-----------------+-------------------+-----
PREV.   NEXT  
|<   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51  
52   53   54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   >>   >|  



Top keywords:

shields

 

shield

 

pockets

 

Island

 

position

 

middle

 

polings

 

allowed

 

pressure

 

cutting


shoved

 

Manhattan

 
method
 

driven

 

bulkheads

 
concrete
 

temporary

 

precaution

 

arrangement

 
receive

shaped

 

removal

 

rested

 

accomplished

 
PROGRESS
 

NATURE

 

MATERIALS

 
careful
 

handling

 

METHODS


ISLAND

 

TUNNELS

 
ADOPTED
 

CONSTRUCTION

 

desired

 

alignment

 

varying

 
distances
 
forward
 

bulkhead


negligible

 

surveys

 

workings

 

excavation

 

errors

 

bottom

 

planks

 
Toward
 

natural

 

hydrostatic