FREE BOOKS

Author's List




PREV.   NEXT  
|<   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28  
29   30   31   32   33   34   35   36   37   38   >>  
ll surface vehicular and pedestrian traffic. All structures were left in place with the exception of the pipes, most of which were temporarily cut out. The 48-in. brick sewer in the center of Ninth Avenue was broken, and the sewage was pumped across the excavation through a smaller pipe. The general method adopted was as follows: The east and west sides of the avenue were closed, vehicular traffic was turned into the center, and a trestle for pedestrians was constructed west of the westerly elevated railway columns. All structures were then supported on transverse girders, running across the avenue, below the surface, and these rested on concrete piers on the central rock core. The sides of the avenue were then excavated to sub-grade, and the permanent steel viaduct was erected on both sides of the avenue as close as possible to the central rock core. The weight of all structures was then transferred to the permanent steel viaduct, erected on the sides of the avenue, by timber bents under the transverse girders resting on the permanent steel viaduct, and all weight was thus taken off the central rock core. This core was then excavated to sub-grade, the permanent viaduct was completed, and all structures were placed on its deck, using concrete piers and timber bents. The design and erection of the permanent steel viaduct and the permanent foundations on its deck were done under another contract, apart from the North River Division work, and are not described in this paper. _Elevated Railway Structure of the Interborough Rapid Transit Company._--The Ninth Avenue Elevated Railway was built between 1877 and 1880 as a two-track structure, the design being such as to permit a third or central track to be added later, and this was built in 1894. It is supported on columns under the outside tracks, about 43 ft. from center to center longitudinally and 22 ft. 3 in. from center to center transversely, the central track being carried by transverse girders between the columns. The columns carrying the structure are of fan top design, with the points of bearing near the extremities at the top; each of the outside tracks is supported on two longitudinal latticed girders and the central track on two plate girders; between the columns, transverse girders are spliced to the outside track cross-frames, and carry the central track system. It was not thought desirable to put brackets on the columns near the street level to support the
PREV.   NEXT  
|<   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28  
29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

central

 
girders
 
center
 

columns

 
permanent
 
viaduct
 
avenue
 

structures

 

transverse

 

supported


design
 
structure
 

tracks

 
excavated
 
concrete
 

weight

 
timber
 

erected

 

Railway

 

Elevated


surface

 

Avenue

 

traffic

 

vehicular

 

pedestrian

 

permit

 

Company

 
Transit
 
Interborough
 

exception


system

 

frames

 
spliced
 

thought

 

desirable

 

support

 

street

 

brackets

 

latticed

 
longitudinal

carried

 

carrying

 

transversely

 

Structure

 
points
 

extremities

 

bearing

 

longitudinally

 

smaller

 

general