FREE BOOKS

Author's List




PREV.   NEXT  
|<   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33  
34   35   36   37   38   >>  
n each side is put in place. No. 5 Two outside Concrete Piers removed and 6th row of Permanent Steel in place. Girders _C_ carrying all structures now resting on Bents on Permanent Steel. 48" C.l. Sewer carried on Brackets on Girders _C_. No. 6 Excavation Completed. ] Temporary raker braces were placed against the structure to prevent lateral movement. Four sets of these temporary shoring girders were used in this manner, two sets starting at the north end and two sets at about the middle of the work, and these sets were moved south as they were released. The columns being thus supported on temporary shoring girders, the old foundations were removed and the excavation was taken down to a level about 16 ft. below the surface. Two sets of three of the girders "C" were then put in place under the avenue at each column, each set being placed on four concrete piers 6 ft. square with spaces of 4 ft. between them, so that the outside of the outside pier would be 18 ft. from the center of the avenue and 32 ft. from the house line. This is shown on Fig. 5 and on Fig. 3, Plate XLVII. Four small piers were used, as they could be more easily removed than one continuous pier. The girders "C" were set to line and grade, and the piers were built under them, great care being taken to get the concrete well under the girders so as to give a firm bearing. After these girders "C" were in place it was necessary to remove the temporary shoring girders before the bents could be erected on girders "C" to support girders "B," being in the same plane; and provision had to be made to support the structure while this was being done. Therefore, double bents were erected directly beneath the columns, as shown by Figs. 2, 4, and 5, and by Fig. 3, Plate XLVII. These were built with their sills resting on the girders "C," and blocking was put in between the sills and the rock to carry the full weight of the structure. Later, when the weight of the structure was carried on the permanent bents, this blocking was knocked out, but the bents were left in to carry the weight of the column itself, which was swinging more or less from the structure above. The weight of the structure was placed on these bents directly beneath the columns by jacking up the temporary girders again, putting blocking between the bents and the base of the columns, and taking out the blocking which had been put in previously under the temporary shoring girders. The 24
PREV.   NEXT  
|<   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33  
34   35   36   37   38   >>  



Top keywords:

girders

 
structure
 
temporary
 

shoring

 
columns
 
weight
 
blocking
 

removed

 

avenue

 

column


concrete
 
directly
 

support

 
erected
 
beneath
 

carried

 
Girders
 

resting

 

Permanent

 

taking


provision

 

double

 

Therefore

 

bearing

 

remove

 

previously

 

carrying

 
knocked
 
permanent
 

jacking


swinging

 

Concrete

 
putting
 

surface

 

manner

 

movement

 

square

 

prevent

 

lateral

 
middle

released

 

supported

 

starting

 

excavation

 
foundations
 

spaces

 

braces

 

structures

 

easily

 

continuous