FREE BOOKS

Author's List




PREV.   NEXT  
|<   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37  
38   >>  
removal of girders "C." [Illustration: FIG. 6. (Full page image) GENERAL ARRANGEMENT OF TEMPORARY AND PERMANENT STRUCTURES] During the latter part of 1908 a 48-in. cast-iron water main was laid by the city on a cradle built by the Railroad Company on girders "C" on the east side of the avenue. This is part of the high-pressure system, and the location and elevation of this water main were taken into consideration when the underpinning was designed. This main, and the 48-in. cast-iron sewer bracketed to girders "C," are shown on Fig. 4, Plate XLVIII. Elevations had been taken on marks on the elevated railway columns between 30th and 34th Streets at the time the original surveys were made, in 1902, and these marks were used to test the level of the structure during the progress of the excavation. At the extreme south end of the work the procedure was changed. The east side was excavated down to sub-grade, the east portion of the south abutment was constructed, and six rows of the permanent steel viaduct were erected. Very little excavation had been done on the west side of the avenue at the south end of the work, and it would have delayed the completion of the work to have waited for the excavation for and the construction of the west portion of the south abutment and the erection of the steel; therefore, instead of supporting the girders "C" on the central rock core, the east ends were taken up on the permanent viaduct girders, and the west ends were supported on a concrete pier on the rock. The central portion of the avenue was excavated in advance of the west portion. The permanent viaduct girders were put in place from east to west across the avenue, and the girders "C" were supported on the deck of the permanent viaduct approximately under the west elevated railway columns before the west portion of the avenue was excavated, the central portion of the south abutment having been constructed before the west portion. This procedure was adopted only at the north girders "C" at elevated railway column No. 488, the south set of girders "C" being on the rock immediately south of the south abutment. Figs. 2 and 4, Plate XLIX, and Fig. 2, Plate LII, show various stages of the work at the south end. [Illustration: PLATE XLIX, FIG. 1.--TW 60, P.T. & T.R.R. Co. Terminal Station West. Under Ninth Ave., looking South from North abutment, showing underpinning and excavation of rock core. Aug. 13, 08.] [Illustration:
PREV.   NEXT  
|<   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37  
38   >>  



Top keywords:

girders

 
portion
 
avenue
 

abutment

 
permanent
 
viaduct
 
excavation
 

elevated

 

railway

 

Illustration


central
 
excavated
 

procedure

 
underpinning
 
columns
 

supported

 
constructed
 

advance

 

delayed

 

approximately


completion

 

concrete

 

supporting

 

erection

 

construction

 

removal

 

waited

 
Terminal
 
Station
 

stages


showing

 

column

 
adopted
 

immediately

 

designed

 

consideration

 

TEMPORARY

 

bracketed

 

Elevations

 
XLVIII

elevation

 

location

 

cradle

 

Railroad

 
During
 

Company

 

STRUCTURES

 

system

 

pressure

 

PERMANENT