FREE BOOKS

Author's List




PREV.   NEXT  
|<   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31  
32   33   34   35   36   37   38   >>  
I-beams bracketed to the ends of the transverse girders, as shown on Figs. 1 and 2. [Illustration: FIG. 2. (Full page image) METHOD OF SUPPORTING ELEVATED RAILWAY STRUCTURE] [Illustration: FIG. 3. (Full page image) METHOD OF SUPPORTING TRACKS OF NEW YORK CITY RAILWAY CO.] _Girders "C."_--The transverse girders below the street surface, referred to above, were known as girders "C," and they were put in place at first resting on concrete piers on the central core; the weight of all structures was placed on them while the sides of the avenue were being excavated, and the sides of the viaduct were being built. The ends of these girders were then picked up on the sides of the viaduct, and, spanning the central rock core, carried all structures while the core was being excavated and the viaduct completed. New foundations were then placed on the deck of the viaduct to carry all structures. Fifty-four of these girders were required, each weighing about 19,000 lb. The bents carrying the ends of these girders on the sides of the viaduct are shown on Fig. 2. They were of long-leaf yellow pine. These girders were located so that a cradle could be laid on them east of the elevated railway structure to carry a proposed 48-in. cast-iron water main. _Girders "B."_--Eighteen of these girders were required, each weighing about 6,000 lb. The timber bents supporting these girders, shown on Fig. 2, were of long-leaf yellow pine. The total weight, including the elevated railway structure, surface railway structure, pipes, etc., supported during the work, amounted to about 5,000 tons. _Details of the Work._--The method in general is shown on Figs. 4 and 5. At first the east side of the avenue was closed and excavated down to rock, the earth was mined out under alternate yokes of the surface railway structure, and temporary posts were placed under the yokes to support the structure while the remainder of the earth was being removed. Then needle-beams and posts were placed under each yoke. The concrete forming the track structure was then enclosed with planking to prevent it from cracking and falling. I-beams were then placed under the needle-beams carrying the structures, and these were carried on posts; they were changed alternately until the excavation had been taken out to a depth of about 16 ft. below the surface. In placing these I-beams, heavier blocking was used in the center of the span than at the ends where the ben
PREV.   NEXT  
|<   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31  
32   33   34   35   36   37   38   >>  



Top keywords:

girders

 
structure
 
viaduct
 

structures

 
railway
 
surface
 
excavated
 

avenue

 

carried

 

elevated


needle
 
yellow
 

weighing

 
required
 
carrying
 

transverse

 
weight
 

Girders

 

METHOD

 

Illustration


concrete

 

central

 

RAILWAY

 

SUPPORTING

 

support

 

removed

 

remainder

 
temporary
 
general
 

method


Details

 

bracketed

 
closed
 

alternate

 

placing

 

heavier

 

blocking

 

center

 

prevent

 
planking

enclosed

 

forming

 

cracking

 

excavation

 
alternately
 

changed

 

falling

 

supporting

 

street

 

TRACKS