FREE BOOKS

Author's List




PREV.   NEXT  
|<   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
re demolition. View of South side showing chutes. Jan. 21, 09.] [Illustration: PLATE LI, FIG. 4.--A 54. P.R.R. Tunnels, N.R. Div. Sect. Gy. West & Oj. View across North River on line of Tunnels, looking from New York to New Jersey. Feb. 9, 07.] In the first few sections of wall, the form was filled to within 1 in. of the top of the bridge seat and allowed to set for about 2 hours; it was then finished to the proper elevation with a plaster of 1 part of cement to 1 part of sand. This did not prove satisfactory, as there were indications of checking and cracking, and, later, the form was filled to the required elevation and the surface floated. The form was allowed to remain in place for from 18 to 24 hours, depending on the weather. In most cases, immediately after the form had been moved, a scaffold was erected against the face of the wall, and the face was wet and thoroughly rubbed, first with a wooden float and then with a cement brick, until the surface was smooth and uniform. The section 1 ft. square at the top of the bridge seat, which was left out in order to brace the bottom of the form for the upper face wall, was filled in after the walls had been completed. The old concrete was very thoroughly cleaned before the new concrete was placed on it, and a gutter was formed at the rear connecting with the box drains back of the wall to carry off rain-water coming down the face of the upper walls. In hot weather the walls were thoroughly wetted down several times a day for several days after the form had been removed. _Upper Face and Retaining Wall._--In cases where the top of the retaining wall was at a higher elevation than the mixer, it was necessary to raise the concrete in a bucket with a derrick, and dump it into cars on the trestle above the top of the coping. Concrete was deposited through chutes, as in the lower face wall, continuously from the bottom of the face wall to the top of the retaining wall. At the commencement of each section of the retaining wall a layer of mortar was put on the rock. A 1:2:3 mixture of concrete was used in the face wall, and a 1:3:6 mixture in the retaining wall. As the face walls were so thin, the number of batches of concrete per hour was reduced, for the form filled so rapidly that the concrete, before it set, exerted an excessive pressure against the form, and this tended to make it bulge. The proper rate at which to place the concrete behind a form 50 ft. long, wi
PREV.   NEXT  
|<   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

concrete

 
filled
 
retaining
 

elevation

 
allowed
 
proper
 
surface
 

bottom

 

mixture

 

cement


weather
 
section
 

chutes

 
bridge
 
Tunnels
 

Retaining

 
higher
 

trestle

 

derrick

 

bucket


connecting

 

drains

 

coming

 

showing

 

removed

 

wetted

 

deposited

 
exerted
 
excessive
 

rapidly


reduced

 

pressure

 
tended
 

batches

 

number

 

commencement

 

continuously

 

Concrete

 

mortar

 
demolition

coping

 

checking

 

cracking

 

indications

 
satisfactory
 

required

 

depending

 

remain

 

floated

 

finished