FREE BOOKS

Author's List




PREV.   NEXT  
|<   29   30   31   32   33   34   35   36   37   38   >>  
nnel work west of Tenth Avenue, and these lines, together with bench-marks similarly established, were used in laying out the Terminal Station-West work. Prior to the commencement of the work, elevations were taken on the surface at 10-ft. intervals, and elevations of the rock surface were taken on these points as the rock was uncovered. Cross-sections were made and used in computing the progress and final estimates. Very careful records were kept of labor, materials, derrick performances, steam-shovel performances, quantity of dynamite used, etc., and, in addition, a diary was kept giving a description of the work and materials used each day; various tables and diagrams were also prepared. A daily report was sent to the Chief Office showing the quantities of excavation removed and concrete built, the force in the field, the plant at work, etc., during the previous day. At the end of each month a description of the work done during that month, with quantities, force of men employed, percentages of work done, etc., was sent to the Chief Office. Two diagrams, showing cross-sections and contours of the excavation done and the progress of the concrete walls, were also sent. COST ACCOUNT. From the records of labor and material obtained in the field, and from estimated charges for administration and power, an estimate was made of the cost to the contractor for doing various classes of work. It was necessary to estimate the administration and power charges, as the contractor's organization and power-house were also controlling and supplying power to the Terminal Station work east of Ninth Avenue and also the work below sub-grade. The labor and material charges in the field were placed directly against the class of work on which they were used and the administration and general charges (which included superintendence, lighting, etc.) were apportioned to the various classes of work in proportion to the value of the labor done. STATISTICS. The total weight of the structural steel used during the underpinning of Ninth Avenue was 1,475,000 lb. The total weight supported during the work under Ninth Avenue was about 5,000 tons. \U$1\EThe average daily traffic over the Ninth Avenue Elevated Railway was 90,000 passengers, and, during the progress of the excavation and underpinning, about 100,000,000 passengers were carried over that structure. The total excavation was 521,000 cu. yd., of which 87% was solid ro
PREV.   NEXT  
|<   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

Avenue

 
charges
 
excavation
 

progress

 
administration
 
showing
 
Office
 

diagrams

 

description

 

quantities


underpinning
 
weight
 

passengers

 
classes
 
contractor
 

performances

 
material
 

estimate

 

concrete

 

records


surface

 

sections

 

elevations

 

Terminal

 

Station

 

materials

 

general

 
included
 
proportion
 

STATISTICS


apportioned

 

lighting

 
superintendence
 

supplying

 

controlling

 

structural

 

laying

 

directly

 

carried

 
Elevated

Railway

 

structure

 

traffic

 

supported

 
established
 

similarly

 

average

 

uncovered

 

report

 

computing