FREE BOOKS

Author's List




PREV.   NEXT  
|<   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
or the upper face wall could be braced against it. The top of this form was tied by cables attached to rods in the rock and by rods with turnbuckles running from back to front of the form; braces were also put in from the back of the retaining wall form to the walls of buildings along the property lines, when this could be done. The middle section of the form was held by rods with turnbuckles which passed through the form and were fastened to each of the tie-rods drilled into the rock, as was also done in the case of the lower face wall. It was generally possible to hold the form to true position in this manner, but occasionally it had a tendency to bulge; when this occurred, the rods leading through the form and fastened to the tie-rods were tightened up, the placing of the concrete was slowed up, and no serious bulging occurred. Bulkheads at the ends of the sections were built of rough planking securely braced to the rock, except that a planed board was laid up against the face of the form to make a straight joint. At the end of each section a V was formed, as shown by Fig. 1, Plate LI. At all corners, a "return," or portion of the wall running at right angles, was built, and no section of wall was stopped at a corner. _Filling Forms of Lower Face Walls._--A temporary trestle was erected above the elevation of the bridge seat, and a track, leading from the mixer to the form to be filled, was laid on it. At the commencement of each section a layer of mortar (1 part of cement to 2-1/2 parts of sand) was deposited on the bottom. A 1:3:6 mixture of concrete was used; it was run from the mixer into dump-cars and deposited in the form through chutes, three of which were provided for each 50-ft. section, the average length. The concrete was mixed wet, and was not rammed; the stone was spaded back from the face, and no facing mixture or facing diaphragms were used. Work on each section was continued day and night without any intermission from the time of commencement to the time of completion. At frequent intervals the box drains were washed out thoroughly with a hose, in order to prevent them from clogging up with grout. [Illustration: PLATE LI, FIG. 1.--TW 66, P.N.Y. & L.I.R.R. Terminal Station West. Box drains and tie rods, South side, Sta. 184+80 to 185+14. Sept. 17, 08.] [Illustration: PLATE LI, FIG. 2.] [Illustration: PLATE LI, FIG. 3.--P 46. P.R.R. Tunnels, N.R. Div. Sect. Gy. West. Disposal trestle just befo
PREV.   NEXT  
|<   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

section

 
concrete
 
Illustration
 

facing

 
drains
 
occurred
 
leading
 

turnbuckles

 

deposited

 

mixture


commencement
 
running
 

fastened

 
trestle
 
braced
 

spaded

 
bottom
 

diaphragms

 

continued

 

chutes


provided

 

average

 

length

 

rammed

 

Disposal

 

Tunnels

 

Station

 
Terminal
 
washed
 

completion


frequent

 

intervals

 
prevent
 

clogging

 

intermission

 

return

 

position

 

manner

 

occasionally

 
generally

tendency

 

bulging

 

Bulkheads

 

slowed

 
tightened
 

placing

 

braces

 

attached

 

cables

 

retaining