FREE BOOKS

Author's List




PREV.   NEXT  
|<   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26  
27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   >>   >|  
he unit costs of the work. These are given in two parts: The first is called the unit labor cost, and is the cost of the labor in the tunnel directly chargeable to the thing considered. It does not include the labor of operating the plant, nor watchmen, yardmen, pipemen, and electricians. The second is called "top charges," a common term, but meaning different things to different contractors and engineers. Here, it is made to include the cost of the contractor's staff and roving laborers, such as pipemen, electricians, and yardmen, the cost of the plant and its operation, and all miscellaneous expenses, but does not include any contractor's profit, nor cost of materials entering permanent work. The contractor's plant is to be described in a paper by Henry Japp,[B] M. Am. Soc. C. E., and will not be dealt with here. The contractors carried on their work from three different sites. From permanent shafts, located near the river in Manhattan, four shields were driven eastward to about the middle of the river; and, from two similar shafts at the river front in Long Island City, four shields were driven westward to meet those from Manhattan. From a temporary shaft, near East Avenue, Long Island City, the land section of about 2,000 ft. was driven to the river shafts. [Footnote A: Presented at the meeting of December 15th, 1909.] [Footnote B: _Transactions_, Am. Soc. C. E., Vol. LXIX. p. 1.] TUNNELS FROM EAST AVENUE TO THE RIVER SHAFTS. The sinking of the temporary shaft at East Avenue was a fairly simple matter. Rough 6 by 12-in. sheet-piling, forming a rectangle, 127 by 34 ft., braced across by heavy timbering, was driven about 28 ft. to rock as the excavation progressed. Below this, the shaft was sunk into rock, about 27 ft., without timbering. As soon as the shaft was down, on September 30th, 1904, bottom headings were started westward in Tunnels _A_, _B_, and _D_. When these had been driven about half the distance to the river shafts, soft ground was encountered. (See Station 59, Plate XIII.) As the ground carried considerable water, it was decided to use compressed air. Bulkheads were built in the heading, and, with an air pressure of about 15 lb. per sq. in., the heading was driven through the soft ground and into rock by ordinary mining methods. The use of compressed air was then discontinued. West of this soft ground, a top heading, followed by a bench, was driven to the soft ground at about Station 66.
PREV.   NEXT  
|<   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26  
27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   >>   >|  



Top keywords:

driven

 

ground

 

shafts

 
contractor
 

include

 
heading
 

Station

 

compressed

 

carried

 
westward

Island

 

temporary

 

Avenue

 

permanent

 

Footnote

 

Manhattan

 

shields

 
timbering
 
called
 
contractors

pipemen

 

electricians

 
yardmen
 

September

 

headings

 

Tunnels

 

started

 
bottom
 

rectangle

 

braced


forming

 

piling

 

progressed

 

excavation

 

directly

 

tunnel

 

pressure

 
ordinary
 

mining

 
discontinued

methods

 

Bulkheads

 

encountered

 

distance

 

decided

 

considerable

 

SHAFTS

 

engineers

 

located

 

things