FREE BOOKS

Author's List




PREV.   NEXT  
|<   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29  
30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   >>   >|  
ted; second, the reduction of the sewer in Eighth Avenue from a 6-ft. to a 5-ft. circular conduit; and, third, assuming that the sewage and drainage from the Terminal would be pumped directly to the sewers in the avenues, the reduction of the sewers in 31st and 33d Streets, from Seventh to Ninth Avenue, to 15-in. vitrified pipes, except west of the Service Building in 31st Street, to accommodate which section, a larger sewer was required. The sewer in 32d Street, from Ninth to Eighth Avenue, of course, could be dispensed with in any arrangement, as all the area tributary to it was to be excavated. [Illustration: Fig. 2. PLAN SHOWING LAYOUT OF SEWER IN CATCHMENT AREA ABOUT TERMINAL STATION] GAS AND WATER MAINS. A rearrangement of the gas pipes in the three streets crossing the Terminal site was necessary. These pipes were of two classes: trunk mains and service mains. Fortunately, there were but two trunk mains in the three streets, one a 20-in. in 31st Street from east of Seventh Avenue to Ninth Avenue, the other a 16-in. in 32d Street from east of Seventh Avenue to Eighth Avenue. The 20-in. main was relaid from Seventh Avenue and 31st Street down Seventh Avenue to 30th Street and through that street to Ninth Avenue. The 16-in. main was relaid from Seventh Avenue and 32d Street north to 34th Street and through that street to Eighth Avenue. The service mains in 32d Street were no longer required, and were taken up and not replaced. The houses on 31st and 33d Streets were provided with service by two 6-in. wrought-iron mains back of the retaining walls in each street, that location being chosen to avoid damage by gas drip to the water-proofing of the street bridges. As the permanent structures under the avenues were not to approach the surface nearer than 19 ft., only slight rearrangements, sufficient to permit the new sewers and water lines to be laid, were necessary. There were no large water mains to be cared for, in fact, those in the streets were too small for ample fire protection, being only 6 in. in diameter. The main in 32d Street was taken up and not replaced, and those on 31st and 33d Streets were replaced by 12-in. pipes laid back of the retaining walls. No changes were necessary in the mains in the avenues, but, before approving the rearrangement for the streets, the Department of Water Supply, Gas and Electricity added a 48-in. main in Eighth Avenue to be laid as a part of this construction,
PREV.   NEXT  
|<   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29  
30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   >>   >|  



Top keywords:

Avenue

 

Street

 

Seventh

 

Eighth

 
street
 

streets

 

service

 

Streets

 

replaced

 

avenues


sewers

 

reduction

 

rearrangement

 
relaid
 
required
 
Terminal
 

retaining

 

chosen

 

damage

 

wrought


provided

 

houses

 

proofing

 
location
 

approving

 

diameter

 
protection
 
Department
 

construction

 
Supply

Electricity
 

surface

 
nearer
 

approach

 
permanent
 

structures

 

slight

 
rearrangements
 

sufficient

 

permit


bridges

 
section
 

larger

 

accommodate

 
Service
 

Building

 

dispensed

 

tributary

 
arrangement
 

conduit