FREE BOOKS

Author's List




PREV.   NEXT  
|<   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50  
51   52   53   54   55   56   57   58   59   >>  
upply piles; the temperature of the mix was taken frequently, and was kept above 40 degrees. Numerous tests made while the work was in progress showed that, while the temperature fell slightly soon after the concrete was deposited, it was always from 2 deg. to 5 deg. higher at the end of 2 hours. The face and back of the concrete were prevented from freezing by a liberal packing of salt hay just outside the forms. A vertical hog trough, 24 in. wide and 9 in. deep, was placed in one end of each section, for its full height below the bridge seat, into which the next section keyed, and, when the temperature at the time of concreting was below 50 deg. Fahr., a compression joint was formed by placing a strip of heavy deadening felt, 2 ft. wide, on the end of the completed section next to the face and covering the remainder of the end with two ply of the felt and pitch water-proofing; the one ply of deadening felt near the face was about the same thickness as the two ply of water-proofing, and was used to prevent the pitch from being squeezed out of the joint to the face of the wall. The excavation for the retaining walls in 31st and 33d Streets were in all cases made of sufficient width to receive the sewers, which were laid as soon as the back-fill, carefully rammed and puddled, had reached the proper elevations; the back-filling was then completed, and the gas and water mains were afterward laid in separate trenches. [Illustration: Fig. 8. SKETCH SHOWING FORMS AND BRACING FOR NINTH AVENUE WALL] The sections of concrete built in trench varied in height from 13 to 59 ft. from the base to the top of the back wall. With the exception of the Seventh Avenue wall, 50 ft. in height, and the Ninth Avenue wall, 62 ft. in height, none of those sections constructed by the bench method was more than 14 ft. The forms and bracing for these walls were substantially the same, except that the low walls were built in lengths of approximately 50 ft., while the forms for the Seventh and Ninth Avenue walls were only 20 ft. long. The forms and bracing for the Ninth Avenue walls are shown on Fig. 8. These forms were built in one piece and moved ahead from section to section, and they were firmly braced from the bottom with raker braces to a point 36 ft. above the base, the upper part being held in place by 3/4-in. bolts passed through the forms and anchored by cables to bolts grouted into the rock behind. After the forms had b
PREV.   NEXT  
|<   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50  
51   52   53   54   55   56   57   58   59   >>  



Top keywords:
section
 

Avenue

 

height

 

temperature

 
concrete
 

deadening

 
completed
 

sections

 
proofing
 
Seventh

bracing

 

cables

 

grouted

 

varied

 

trench

 
passed
 
exception
 

anchored

 

AVENUE

 
trenches

Illustration

 

separate

 

afterward

 

BRACING

 

SKETCH

 

SHOWING

 

approximately

 

braces

 
firmly
 
braced

bottom

 
lengths
 

constructed

 

method

 

substantially

 

vertical

 

trough

 
concreting
 

Numerous

 
bridge

slightly

 

higher

 

deposited

 
prevented
 
freezing
 

packing

 

showed

 

progress

 

liberal

 

degrees