FREE BOOKS

Author's List




PREV.   NEXT  
|<   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45  
46   47   48   49   50   51   52   53   54   55   56   57   58   59   >>  
ll sharpeners, and one oil blower forge. _2._--_Retaining-Wall Plant._ The retaining-wall plant was identical with that described for the first period, with the addition of two Ransome 1-cu. yd., concrete mixers, with vertical engines mounted on the same frame, using compressed air. _3._--_Pit-Excavating Plant._ The pit-excavating plant included that listed for the first period and, in addition, the following: One Vulcan, 30-ton, steam shovel, with 1-cu. yd. dipper and a vertical boiler. One Ohio, 30-ton, steam shovel, with 1-cu. yd. dipper and a vertical boiler. Four guy derricks (50 to 80-ft. masts and 45 to 60-ft. booms), operated by Lambert 7 by 10-in. engines, with two drums and swinging gear, mounted with 25-h.p. vertical boilers, but driven by compressed air. Seventy Ingersoll-Rand rock drills, Nos. 1, 31/4, and 4. Two Rand quarry bars, cutting 10 ft. in length at one set-up, and mounted with No. 4 drill using a Z-bit. _4._--_Transportation Plant._ Twenty-one H. K. Porter locomotives, 10 by 16-in., and 36-in. gauge. Three Davenport locomotives, 9 by 16-in., and 36-in. gauge. One hundred and forty Western dump-cars, each of 4 cu. yd. capacity. One hundred and sixty-five flat cars, with iron skips, each of 4 cu. yd. capacity. _5._--_Dock Plant._ Four stiff-leg derricks on extension, having 35-ft. masts and 40-ft. booms, and each operated by a 60-h.p. Lambert, three-drum, electric, hoisting engine. One stiff-leg derrick, on the south side of the pier on the upper deck, with a 28-ft. mast operated by a three-drum Lambert engine and a 25-h.p. vertical boiler. One stiff-leg derrick, on the north side of the dock on the upper deck, used exclusively for bringing in brick, electric conduit, pipe, and other building material, operated when first erected by a three-drum, steam-driven, Lambert, hoisting engine. This engine was later changed to the derrick on the south side of the dock, and a motor-driven Lambert engine from that derrick was substituted. Eight electric telphers. Ninth Avenue Twin-Tunnels Plant. One stiff-leg derrick, previously used in retaining-wall work. One Smith concrete mixer, 1 cu. yd. capacity, driven by attached air engine. Two cableways taken from the retaining-wall plant and used for mucking out the tunnels after the center pier had been built;
PREV.   NEXT  
|<   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45  
46   47   48   49   50   51   52   53   54   55   56   57   58   59   >>  



Top keywords:

engine

 

derrick

 

vertical

 

Lambert

 

operated

 

driven

 

retaining

 

boiler

 

mounted

 
capacity

electric

 
hundred
 
hoisting
 

locomotives

 
addition
 

period

 

engines

 

concrete

 
compressed
 

shovel


dipper

 

derricks

 

sharpeners

 
bringing
 
conduit
 

Ransome

 

exclusively

 

blower

 

identical

 

Retaining


extension

 
cableways
 

attached

 

mucking

 

center

 

tunnels

 

previously

 

Tunnels

 
changed
 

erected


material
 
substituted
 

Avenue

 

telphers

 

building

 

drills

 

Seventy

 
Ingersoll
 

Excavating

 
cutting