FREE BOOKS

Author's List




PREV.   NEXT  
|<   46   47   48   49   50   51   52   53   54   55   56   57   58   59   >>  
herefore, were of great advantage where track room and scow berths were limited. As noted in the list of contracts under which the work was executed, the scows at both the 35th Street dumping board and Pier No. 72 were furnished, towed, and the material finally disposed of, by Henry Steers, Incorporated. During the same period, this contractor disposed of the material excavated from both the Cross-town Tunnels, constructed by the United Engineering and Contracting Company, and the tunnels under the East River, constructed by S. Pearson and Son, Incorporated. As stated in other papers of this series relating to the construction of those tunnels, the material excavated by the United Engineering and Contracting Company was delivered to barges at 35th Street and East River and that by S. Pearson and Son, Incorporated, at two points, one in Long Island City and the other at 33d Street and East River, Manhattan. The total number of cubic yards of material disposed of amounted to: Place measurement. Total barge Earth. Rock. measurement. 35th Street and North River 242,800 22,800 281,500 Pier No. 72, North River 673,800 1,488,000 3,203,400 From Cross-town Tunnels 570,400 From Under-river Tunnels 402,500 ----------- Total 4,457,800 =========== The material was delivered as follows: To the freight terminal of the Pennsylvania Railroad Company at Greenville, N.J. 3,454,800 To the Meadows Division of the Tunnel Line between Harrison, N.J., and the North River Portals 711,900 To other points selected by the contractors 291,100 --------- Total 4,457,800 ========= The handling of this large quantity of material required the loading of from 10 to 20 scows per day (and for more than two years the average was 14), and, as the average time spent in one round trip was 3 1/3 days, a fleet of more than 50 scows was required to keep all points supplied and allow for a fe
PREV.   NEXT  
|<   46   47   48   49   50   51   52   53   54   55   56   57   58   59   >>  



Top keywords:

material

 

Street

 
points
 

disposed

 
Tunnels
 

Company

 
Incorporated
 
tunnels
 

Contracting

 

Engineering


constructed
 
delivered
 

measurement

 

Pearson

 

United

 
average
 

required

 

excavated

 
terminal
 

Railroad


Pennsylvania

 

Greenville

 
supplied
 

freight

 

handling

 

quantity

 

loading

 
contractors
 
Tunnel
 

Division


Harrison

 

Portals

 

selected

 
Meadows
 
Manhattan
 

finally

 

furnished

 
executed
 

dumping

 

Steers


contractor

 
stated
 

period

 
During
 

advantage

 
herefore
 

contracts

 

limited

 

berths

 

papers