driven by air
supplied to the original engine.
One Robbins belt conveyor, driven by a 30-h.p. engine run by air.
Three 1-cu. yd. Hopple dump-cars.
CONSTRUCTION.
Ground was broken for work under the principal contract on July 9th,
1904, on which date the contractor began cutting asphalt for Trench No.
1 in 31st Street, and also began making a roadway from Ninth Avenue into
the pit just south of 32d Street.
_Excavation for Retaining Walls._--Two essentially different methods
were used in excavating for and building the retaining walls; one,
construction in trench, the other, construction on bench. In general,
the trench method was used wherever the rock on which the wall was to be
founded was 12 ft. or more below the surface of the street; or, what is
perhaps a more exact statement, as it includes the determining factor,
where the buildings adjoining the wall location were not founded on
rock.
In the trench method the base of the wall was staked out on the surface
of the ground, the required width being determined by the elevation of
the rock, as shown by the borings. The contractor then added as much
width as he desired for sheeting and working space, and excavated to a
depth of about 5 ft. before setting any timber. In some cases the depth
of 5 ft. was excavated before the cableway or derrick for the excavation
was erected, the wagons being driven directly into the excavation and
loaded by hand, but, usually, the cableway was first erected, and
buckets were used from the start. After the first 5 ft. had been
excavated, two sets of rangers and struts were set, the first in the
bottom of the excavation and the second at the level of the street
surface, supported by posts resting on the bottom rangers. The sheeting
was then set, and all voids back of it were filled with clean earth and
well tamped. The toe of the sheeting was kept level with the bottom of
the excavation until the ground-water was reached, after which it was
kept from 3 to 5 ft. ahead of the digging.
The sheeting used was 3-in., in variable widths; it was always tongued
and grooved on the side of the trench next to the buildings and in the
deeper excavations on both sides of the trench, and was driven by wooden
mauls above the ground-water level, but steam sheeting-drivers were used
below that elevation. Struts, rangers, and posts were generally 12 by
12-in.
Some exceedingly bad material was encountered in the deeper excavations,
|