FREE BOOKS

Author's List




PREV.   NEXT  
|<   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34  
35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   >>   >|  
Seventh and Ninth Avenues. This refers to the trestles left in place on the completion of the work. (_e_).--The building of a trestle and bridging from a point near the west side of Tenth Avenue on the south side of 32d Street, westward to the outer end of Pier No. 62, at the foot of 32d Street. _2._--The second contract, dated February 10th, 1905, was with the New York Contracting Company-Pennsylvania Terminal, for the excavation for and construction of retaining walls for the Manhattan Terminal Power Station, and the excavation of the area thus enclosed. _3._--The third contract, dated October 2d, 1907, was with the New York Contracting Company-Pennsylvania Terminal, for the construction of two twin tunnels under Ninth Avenue, and other work incidental thereto. Sewers and gas mains laid outside the area covered by the foregoing contracts were constructed under the following agreements: An agreement, dated August 9th, 1904, between the New York Contracting Company-Pennsylvania Terminal, and the New Amsterdam Gas Company, for a 20-in. gas main from Seventh Avenue and 31st Street to 30th Street, and thence to Ninth Avenue, the New Amsterdam Gas Company being remunerated for the cost by the Tunnel Company. A contract, dated August 24th, 1904, with the New York Contracting Company-Pennsylvania Terminal, for the construction of sewers in Seventh Avenue and in 32d and 33d Streets east of Seventh Avenue. A contract, dated November 24th, 1908, with the New York Contracting Company-Pennsylvania Terminal, for the construction of a 16-in. gas main from Seventh Avenue and 32d Street to 34th Street, and thence to Eighth Avenue. All these contracts required that the excavated material be delivered on board scows to be furnished by the company at the pier at the foot of 32d Street, North River. These scows were furnished and the material was disposed of from that point by Henry Steers, Incorporated, under a contract, dated August 9th, 1904, which called for the transportation to and placing of all material so delivered in the Pennsylvania Railroad Company's freight terminal at Greenville, N.Y. The disposal of the excavated material was one of the principal features of the work, and, under the above contract, material from those portions of the Terminal site east of Seventh Avenue and west of Ninth Avenue, and from all substructures work, was disposed of, as well as from the constructions herein descri
PREV.   NEXT  
|<   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34  
35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   58   59   >>   >|  



Top keywords:
Avenue
 

Company

 

Street

 

Terminal

 
Pennsylvania
 

Seventh

 
contract
 

material

 
Contracting
 
construction

August

 

excavated

 

excavation

 

disposed

 

contracts

 
furnished
 
delivered
 

Amsterdam

 

Streets

 
sewers

Tunnel

 

November

 

Eighth

 

required

 

freight

 

terminal

 

Greenville

 

Railroad

 
principal
 
features

portions

 
disposal
 

placing

 

transportation

 

Steers

 

Incorporated

 

called

 
substructures
 

constructions

 
descri

company

 

February

 

Manhattan

 
retaining
 
westward
 

trestles

 

refers

 

Avenues

 

completion

 

bridging