FREE BOOKS

Author's List




PREV.   NEXT  
|<   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49  
50   51   52   53   54   55   56   57   58   59   >>  
ut was removed, the form was built up to the next strut, at front and back, and braced to the sheeting, so that, by the time the entire length of the section had been carried up to the level of the first line of struts, forms were ready at one end for the succeeding layers. The layers of concrete never exceeded 8 in. in height, and at times there were slight delays in the concreting while the carpenters made ready the next lift of forms, but such delays were rarely long enough to permit the concrete to take its initial set. [Illustration: Fig. 7. SKETCH SHOWING FORMS FOR, AND METHOD OF, CONCRETING RETAINING WALLS IN TRENCH.] After a section of concrete had firmly set, both back and front forms were removed, and the thrust from the sides of the trench was transferred directly to the finished wall. The face of the wall was rubbed with a cement brick to remove the marks of the plank, and was then coated with a wash of thin cement grout. The water-proofing and brick armor were then continued up the back of the wall, the spaces between the lines of braces being first water-proofed and bricked, and the braces transferred to the finished surface, after which the omitted panels were completed. The water-proofing consisted of three layers of Hydrex felt, of a brand known as Pennsylvania Special, and four layers of coal-tar pitch. The pitch contained not less than 25% of carbon, softened at 60 deg. Fahr., and melted at a point between 96 deg. and 106 deg. Fahr. The melting point was determined by placing 1 gramme of pitch on a lead disk over a hole, 5/16-in. in diameter, and immersed in water which was heated at the rate of 1 deg. per min.; the temperature of the water at the time the pitch ran through the hole was considered as the melting point. In order to prevent the water-proofing from being torn at the joint between sections when they contract from changes in temperature, a vertical strip of felt, 6 in. wide, was pitched over each joint, lapping 3 in. on each concrete section. The back of this strip was not pitched, but was covered with pulverized soapstone, so that the water-proofing sheet was free from the wall for a distance of 3 in. on either side of each joint. Concreting was continued during the severest weather, one section being placed when the thermometer was 5 deg. above zero. When the thermometer was below the freezing point both sand and stone were heated by wood fires in large pipes under the s
PREV.   NEXT  
|<   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49  
50   51   52   53   54   55   56   57   58   59   >>  



Top keywords:

proofing

 

section

 

layers

 

concrete

 
transferred
 

temperature

 

pitched

 

heated

 

braces

 

melting


continued

 

cement

 

finished

 
removed
 
delays
 
thermometer
 

determined

 

soapstone

 

placing

 

gramme


freezing

 

melted

 

contained

 
lapping
 

pulverized

 

carbon

 
softened
 
considered
 

sections

 
contract

distance
 

prevent

 
Concreting
 

vertical

 
covered
 

severest

 

immersed

 
weather
 

diameter

 

rarely


carpenters

 
slight
 

concreting

 

permit

 
SKETCH
 

SHOWING

 

Illustration

 

initial

 
sheeting
 

entire