FREE BOOKS

Author's List




PREV.   NEXT  
|<   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26  
27   28   29   30   31   32   33   34   35   36   37   38   >>  
e of plans, described in a previous paper, it was decided to sink a third shaft on each line. These were known as the West Shafts, and were located between Sixth and Seventh Avenues. Finally, it was found necessary to build a portion of the tunnels on each line west of Sixth Avenue in open cut. The locations of the shafts are shown on Plate XIV.[C] The First Avenue shafts were built by S. Pearson and Son, Inc., for the joint use of the two contractors, as described in the paper on the tunnels under the East River. While the shafts were being sunk, the full-sized tunnels were excavated westward by the contractor for the river tunnels for a distance of 50 ft., and top headings for 50 ft. farther. By this means, injury to the caissons and to the contractor's plant in the shafts by the subsequent work in the Cross-Town Tunnels was avoided. The west half of the shaft was for the exclusive use of the contractor for the Cross-Town Tunnels. CONTRACTOR'S PLANT. The method of handling the work adopted by the contractor was, broadly speaking, as follows: Excavation was usually carried on by modifications of the top-heading and bench method, the bench being carried as close to the face as possible in order to allow the muck from the heading to be blasted over the bench into the full section. The spoil was loaded into 3-yd. buckets (designed by the contractor and hereinafter described), by steam shovels operated by compressed air, and hauled to the shafts by electric locomotives. Electrically-operated telphers, suspended from a timber trestle, hoisted the buckets, and, traveling on a mono-rail track, deposited them on wagons for transportation to the dock. Arriving at the dock, the buckets were lifted by electrically-operated stiff-leg derricks and their contents deposited on scows for final disposal. The spoil was thus transported from the heading to the scow without breaking bulk. When concreting was in progress, the spoil buckets were returned to the shafts loaded with sand and stone. The concrete materials were deposited in storage bins placed in the shafts, from which they were fed to the mixers located at the foot of the shaft about on a level with the crown of the tunnels. The concrete was transported to the forms in side-dump, steel, concrete cars, hauled by the electric locomotives. Electrical power was adopted largely on account of the restricted area at the shaft sites, where a steam plant would have occupied
PREV.   NEXT  
|<   2   3   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26  
27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

shafts

 

tunnels

 

contractor

 

buckets

 
concrete
 

operated

 

deposited

 
heading
 

adopted

 
method

transported

 

Tunnels

 
Avenue
 

hauled

 

located

 
loaded
 

locomotives

 
electric
 

carried

 

lifted


shovels

 

electrically

 

traveling

 
trestle
 

compressed

 

transportation

 

wagons

 

Electrically

 

hoisted

 

Arriving


telphers

 

timber

 

suspended

 

derricks

 

concreting

 

mixers

 
Electrical
 
occupied
 
largely
 

account


restricted
 

breaking

 

disposal

 

contents

 

hereinafter

 

storage

 

materials

 

progress

 

returned

 

speaking