FREE BOOKS

Author's List




PREV.   NEXT  
|<   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
d bench. Part of the muck handled by hand and part by steam shovel. Exploration drift about 10 ft. by 13 in. Muck loaded by hand. 14 ft. timbered. At portal of twin tunnels. Drift excavated to full width and bench. Muck loaded by hand. 12 ft. timbered. Drift excavated to full width and bench. Muck loaded by steam shovel. Full-width tunnel timbered for 26 ft. independently of the main excavation. ======================================================= THREE-TRACK TUNNEL EXCAVATION. When it became evident that the work through the Fifth Avenue section would be extremely slow, shafts were sunk in each street between Sixth and Seventh Avenues. The shafts, as shown on Plate XIV, were located in the streets, but in such a way as to block only half of the roadway. At the same time it was decided to construct in open cut about 200 ft. of the Three-Track Tunnel at the west end of the contract in 32d Street, where the rock surface was below the top of the tunnel. It was hoped that the remainder of the work could be built without opening the street, but further investigation showed that this was impracticable, and eventually all the Three-Track Tunnel in 32d Street, except 120 ft. east of the shaft, was built in open cut. _Thirty-second Street Work in Tunnel._--Following the sinking of the shaft, a drift was driven across the street at the crown of the tunnel, and a top heading on the south side was excavated in both directions. Frequent cross-drifts to the north side showed that the rock was nowhere very sound and that, except for a short distance east of the shaft, it was distinctly unfavorable for the wide Three-Track excavation. In this stretch the north ends of these cross-cuts were connected by a second heading, and wall-plates and sets of three-segment arch timbering were set up to support the roof of the drifts. The cross-cuttings were gradually widened and timbered until the entire excavation had been made down to the level of the wall-plates, as shown in Fig. 3, Plate LX. The bench was then excavated in two lifts, leaving the wall-plates supported on narrow longitudinal berms, which were removed in short sections to permit the placing of posts under the wall-plates. _Thirty-second Street Open-Cut Work._--Before actual open-cut excavation was started, all buildings facing it were underpinned to rock. For this purpose, a trench was dug along the face of the buildings and of the same depth as
PREV.   NEXT  
|<   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:

plates

 

excavated

 

Street

 

excavation

 
timbered
 

tunnel

 

street

 
Tunnel
 

loaded

 
shafts

buildings

 

Thirty

 
heading
 

shovel

 

drifts

 
showed
 

stretch

 
segment
 

distinctly

 

directions


distance

 

Frequent

 

connected

 
unfavorable
 

placing

 

permit

 

removed

 

sections

 

Before

 

actual


trench

 

purpose

 

started

 

facing

 

underpinned

 

longitudinal

 
narrow
 
widened
 
entire
 

gradually


cuttings
 

support

 

leaving

 

supported

 

timbering

 

surface

 

evident

 

TUNNEL

 

EXCAVATION

 

Avenue