FREE BOOKS

Author's List




PREV.   NEXT  
|<   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29  
30   31   32   33   34   35   36   37   38   >>  
Illustration: PLATE LVIII, FIG. 3.--HEADWORKS AT 33D STREET: INTERMEDIATE SHAFT.] [Illustration: PLATE LVIII, FIG. 4.--LOADING SPOIL ON BARGES, 35TH STREET PIER.] A concrete-mixing plant was placed in each shaft, the mixer being located high enough to discharge into cars at about the level of the springing line of the arch. Above the mixers were the measuring hoppers set in the floor of a platform which was large enough to carry half a day's supply of cement. At the South Shaft the cement was delivered to this floor from the loading platform through a spiral steel chute; at the North Shaft it was lowered in buckets by the telpher. The sand and stone were drawn into the hoppers through short chutes from the base of the storage bins which occupied the remaining height of the shaft--about 50 ft. At the South Shaft the bins were of concrete and steel, about 6 by 12 ft. in section, and attached to the central wall of the caisson. Sand and stone were delivered into them from dump-wagons on the loading platform. At the North Shaft steel-plate bins were used, and were supplied with material by the buckets handled by the telpher. The mixers were No. 5 Smith, belt-connected to 25-h.p. motors, and about 0.8 cu. yd. of concrete was mixed at a batch. The concrete cars were steel side-dumpers of the Wiener or Koppel type. In order to be able to continue concreting during the winter, when neither sand nor stone could be obtained by water, practically all the space under the loading platforms in the South Shaft yards not occupied by the blacksmith shop was filled with these materials, which were placed in storage in the late fall. _Intermediate-Shaft Plant._--The air-compressing plant was located at the rear of the 33d Street Intermediate Shaft, and supplied air for driving the tunnels east and west from the Intermediate Shafts on both 32d and 33d Streets. Two compressors, the same as the large Laidlaw-Dunn-Gordon machine at First Avenue, were installed here, with a similar water-cooling tower. Both shafts were on private property, owned by the Railroad Company, on the north side of the streets, and each was equipped with two telphers supported on timber trestles, similar to those at First Avenue. Here, however, the buckets were placed on wagons standing at the curb, as shown by Fig. 3, Plate LVIII. Blowers for ventilation were installed at each shaft, as at First Avenue, and, after the excavation had proceeded some distan
PREV.   NEXT  
|<   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29  
30   31   32   33   34   35   36   37   38   >>  



Top keywords:

concrete

 

platform

 

loading

 

buckets

 
Avenue
 

Intermediate

 

delivered

 
cement
 

storage

 
telpher

installed

 

occupied

 
similar
 

supplied

 

wagons

 
located
 

STREET

 
mixers
 

Illustration

 

hoppers


Street

 

compressing

 

distan

 
proceeded
 

excavation

 

driving

 

tunnels

 

platforms

 

practically

 

blacksmith


obtained

 

materials

 

Shafts

 

filled

 

winter

 

telphers

 
cooling
 
timber
 
supported
 

equipped


property
 

Railroad

 

private

 

shafts

 

streets

 

Company

 

trestles

 

Blowers

 

Laidlaw

 

ventilation