FREE BOOKS

Author's List




PREV.   NEXT  
|<   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  
encountered about 60 ft. west of Madison Avenue. (See General Viele's map, Plate IX.) Timbering was used for a short distance, and then the heading and bench were narrowed to 18 ft., and steam-shovel excavation was abandoned. As the heading advanced the rock grew steadily softer, the difficult conditions in this locality culminating when a slushy disintegrated feldspar was met, requiring poling and breasting. Thereafter the rock improved markedly, but near the east side of Fifth Avenue its thickness above the roof was found to be only 1-1/2 ft., and the advance was stopped, pending a decision as to a change of plan. [Illustration: PLATE LX, FIG. 1.--DOUBLE ROW OF POSTS UNDER I-BEAMS, SUPPORTING ROOF IN BAD ROCK SECTION.] [Illustration: PLATE LX, FIG. 2.--CENTER WALL AND SKEWBACK UNDER I-BEAMS, AFTER REMOVAL OF DOUBLE ROW OF POSTS.] [Illustration: PLATE LX, FIG. 3.--TIMBERING IN FULL-WIDTH HEADING OF THREE-TRACK TUNNEL.] [Illustration: PLATE LX, FIG. 4.--UNDERPINNING WALLS IN OPEN-CUT SECTION.] After some delay, an exploration drift, similar to the one already described, was driven through to Sixth Avenue, and a change in plan was made, substantially the same as for the 33d Street tunnels. Enlargement to full size was at once started, but, for 400 ft. the rock was very soft and poor, and required extremely careful handling. The exploration drift was widened out to the full Twin-Tunnel width, and I-beams were placed and supported, in much the same manner as in 33d Street. The rock was so soft that it was frequently necessary to drive poling boards ahead as the face was mined out with picks and shovels. The load was very heavy, and the work the most difficult encountered in the tunnels. After this stage of the enlargement was reached, the excavation of the bench and the placing of the lining proceeded alternately, with the I-beams temporarily supported on long posts while the concrete core-wall was being built. Considerable settlement took place while shifting the posts, and eventually showed on the street surface and in the adjacent sidewalk vaults, but no damage was done to the structural portions of the buildings. While the above work had been going on westward from Fifth Avenue, the excavation of the Twin Tunnel eastward from the end of the open-cut section at Sixth Avenue had been proceeding rapidly, and, toward the end of the difficult Fifth Avenue work, it was being attacked from both directions.
PREV.   NEXT  
|<   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:
Avenue
 

Illustration

 

difficult

 

excavation

 
poling
 

supported

 
DOUBLE
 

change

 
SECTION
 
heading

exploration

 

Street

 

tunnels

 

encountered

 

Tunnel

 
required
 
frequently
 

manner

 

widened

 
handling

extremely

 

boards

 

careful

 

shovels

 

alternately

 

portions

 

buildings

 

structural

 
sidewalk
 
vaults

damage

 
westward
 

eastward

 

attacked

 

directions

 

rapidly

 

proceeding

 
section
 

adjacent

 
surface

started

 

temporarily

 

concrete

 
proceeded
 
lining
 

enlargement

 

reached

 

placing

 

shifting

 

eventually