FREE BOOKS

Author's List




PREV.   NEXT  
|<   27   28   29   30   31   32   33   34   35   36   37   38   >>  
side. The felt and pitch water-proofing was then laid for that height, joined to the previous water-proofing on the side-walls, and was followed by the brick armor course over the water-proofing and by the rock packing, after which another lift of brick was laid and the operations were repeated. The large void (Fig. 1, Plate LXII) above the core-wall gave convenient access for working on top of the adjacent sides of the roof, and the keying of the arches and the water-proofing and rock packing above the core-wall were usually carried on from that point, the work progressing from one end. The concrete for all work above the floor was dumped on the platform of the carriages, to which it was transported in the early part of the work in cars running on a high-level track laid on long ties, resting on the finished sidewalks. This arrangement, although requiring a large amount of timber for the track, permitted the muck to be carried out on the low-level track without interference. Later, when the advance of the heading had ceased and the heavy mucking was over, all concrete was transported on the floor level, and the cars were lifted to the carriage platforms by elevators and were hauled by hoisting engines up a movable incline. The latter method is shown by Fig. 3, Plate LIX. _Water-Proofing._--The water-proofing referred to above was in all cases felt and pitch laid with six thicknesses of felt and seven of pitch. The sub-contractor for the work was the Sicilian Asphalt Paving Company. All joints were lapped at least 1 ft., and, where work was suspended for a time and a bevel lap could not be made, the edges of the felt were left unpitched for 1 ft. and the newer work was interlaced with the old. This method was not always successful, however, on account of the softening of the unpitched felt on long-continued exposure to the water. The felt used was mainly "Tunaloid," together with some "Hydrex." It weighed about 12 lb. per 100 sq. ft. when saturated and coated on one side only, and contained about 25% of wool. The coal-tar pitch used had a melting point of 100 deg. Fahr. After the completion of the tunnel, the concrete arch showed some leakage and in places unsightly lime deposits. It was determined to attempt to stop these leaks by the application of a water-proof cement coating on the intrados of the arch. Extended experimental application of two varieties of materials used for this purpose--"Hydrolithic" cement
PREV.   NEXT  
|<   27   28   29   30   31   32   33   34   35   36   37   38   >>  



Top keywords:
proofing
 

concrete

 

carried

 
transported
 

unpitched

 

method

 
application
 

cement

 

packing

 
successful

interlaced

 

materials

 

account

 
unsightly
 
exposure
 

varieties

 

softening

 

continued

 
lapped
 

Hydrolithic


joints

 

Paving

 

Company

 

purpose

 

suspended

 

Tunaloid

 

attempt

 

tunnel

 

contained

 

Asphalt


melting

 

determined

 
coating
 

weighed

 

deposits

 
places
 

Extended

 

experimental

 

Hydrex

 

coated


showed

 

saturated

 
leakage
 

intrados

 

completion

 
carriage
 

progressing

 
dumped
 
platform
 
arches