FREE BOOKS

Author's List




PREV.   NEXT  
|<   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34  
35   36   37   38   >>  
the muck was handled by steam shovels. In the double-heading method, shown on Plate LVII, the top headings for each tunnel of the pair were driven separately, leaving a short rock core-wall between them. The headings were drilled from columns in the manner described for the single tunnels. The temporary rock dividing wall between the headings was drilled by a tripod drill on the bench of one of the headings, and was fired with the bench. In the center-heading method, also shown on Plate LVII, only one heading was driven. It was rectangular in shape, about 8 ft. high and 14 ft. wide. It was located on the center line between the tunnels. In general, the face was from 6 to 12 ft., or the length of one or two rounds, in advance of the remainder of the face at the top. The center heading was drilled by four drills mounted on two columns. By turning these drills to the side, they were used for holes at right angles to the line of the tunnels, by which the remainder of the face of the heading was blasted. By turning the drills downward, the bench holes under the center heading were also drilled. The center heading explored the rock in advance of the full-width heading, and gave a good idea as to the care needed in firing. For the full-width-heading method, Fig. 2, ten drills were mounted on five columns set abreast across the face. Holes were drilled to form a cut near the center line between the tunnels. The remainder of the holes were located so that they would draw into the cut. The bench was frequently drilled from the same set-up of columns by turning the drills downward. In sound rock this method proved to be the most rapid of any. Practically all trimming was left until immediately before the concreting. It was then taken up as a separate operation, but proved to be costly and tedious, and a hindrance to the placing of the lining. _Materials Encountered._--All the rock encountered was the familiar Hudson schist, but it varied widely in its mineral constituents and in its physical characteristics. In many places where the rock surface was penetrated, a fine sand was found that was probably quicksand. The material above the rock in the open-cut sections was mostly sand. [Illustration: FIG. 2. METHOD OF EXCAVATING WITH FULL-WIDTH HEADING CROSS-TOWN TUNNELS, MANHATTAN SIDE ELEVATION FRONT ELEVATION PLAN SHOWING POSITION OF COLUMNS FOR DRILLING FACE] The concurrence of the watercourse, shown on
PREV.   NEXT  
|<   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34  
35   36   37   38   >>  



Top keywords:

heading

 

center

 

drilled

 

drills

 

columns

 

method

 

tunnels

 

headings

 

turning

 
remainder

proved

 
downward
 
mounted
 

advance

 
located
 

driven

 

ELEVATION

 

encountered

 
Encountered
 

watercourse


Materials

 

familiar

 

Hudson

 
trimming
 
widely
 

varied

 

schist

 

COLUMNS

 

concurrence

 

lining


separate

 
immediately
 

concreting

 

operation

 

DRILLING

 

hindrance

 

placing

 

tedious

 
POSITION
 

costly


mineral
 
EXCAVATING
 

quicksand

 

sections

 

Illustration

 

METHOD

 

material

 
HEADING
 

characteristics

 
physical