FREE BOOKS

Author's List




PREV.   NEXT  
|<   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40  
41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  
He added: "We were able to secure these better prices and conditions because the bond market is in a somewhat better condition now than it was when we made the original contract." The contract was accepted on that date, and application made to the Capital Issues Committee for the necessary permission. This was given in due time, though there was considerable opposition. The opposition, said President Thompson, at the Dock Board meeting of February 26, 1919, reviewing the development of the canal plans, "was inspired by vicious and spectacular attacks of certain private interests hostile to the canal project and to the port of New Orleans." Railroads, whose right of way crossed the Canal, were the principal propagandists. They realized that the Dock Board could not be required to build their bridges over the waterway, and although the Thompson board financed the work at the time, they knew that sooner or later would come a day of reckoning. The Hudson Board has since then taken steps to collect several million dollars from these roads. But why build a canal almost large enough, only? Why build a 25-foot lock when ships drawing 30-feet of water come to New Orleans? A lock cannot be enlarged, once it is completed--and the tendency of the times is towards larger ships. Why not make a capacity facility while they were about it? [Illustration: LOCK SITE Driving Sheet Piling] [Illustration: LOCK SITE Dredges Entering] These were questions the Dock Board asked itself, and on June 29, 1918, it decided to build the lock with a 30-foot depth over the sill at extreme low water, and make the canal 300 feet wide at the top, and 150 feet wide at the bottom. To do this, would cost about $1,000,000 more, it was estimated by George M. Wells of the Goethals company--a sum which the Dock Board thought would be realized from the rental-revenues of Doullut & Williams and the Foundation Company, without increasing the second bond issue. This is the Canal that was finally built--nearly 70 per cent larger than the one that was begun and about 100 per cent larger than the one originally planned, when the newspapers and forward-looking told the people that the lack of such a canal had cost New Orleans millions of dollars in development. DIGGING THE DITCH. No rock-problem was encountered in dredging the canal. The cost was below what the engineers estimated it would be--less than thirty cents a cubic yard.
PREV.   NEXT  
|<   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40  
41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  



Top keywords:

larger

 
Orleans
 
Thompson
 

opposition

 

realized

 

estimated

 

development

 

dollars

 
contract
 

Illustration


facility

 

capacity

 

bottom

 

extreme

 

Entering

 

Dredges

 

questions

 

Piling

 

decided

 

Driving


Company
 

millions

 
DIGGING
 

forward

 

newspapers

 

people

 

thirty

 

engineers

 

problem

 

encountered


dredging

 

planned

 

originally

 
thought
 

rental

 

revenues

 

Doullut

 
company
 

George

 

Goethals


Williams

 

Foundation

 

finally

 

increasing

 

million

 

meeting

 

February

 

President

 

considerable

 

reviewing