FREE BOOKS

Author's List




PREV.   NEXT  
|<   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50  
51   52   53   54   55   56   57   >>  
ouldn't be done. The quicksands would flow in too fast. The dredges would drain the surrounding subsoil, but that wouldn't get beyond a certain depth. Furthermore, what assurance was there that the soil that far down would supply sufficient friction to hold the piles necessary to sustain the enormous weight of the lock and the ships passing through it? Undaunted by these croakings, the engineers, from test borings, calculated the sliding and flowing character of the soil, and estimated the various pressures that would have to be counteracted, balanced this with the holding power of pine and steel and concrete, evolved a plan, and began an excavation of a hole 350 feet wide by 1,500 feet long, gradually sloping the cut (1 to 4 ratio) to a center where the lock, 1,020 by 150 feet, outside dimensions, was to be built. [Illustration: INNER HARBOR--NAVIGATION CANAL Lock and Vicinity] The gentle slope of the cut was to prevent slides. It had been ascertained that the first stratum of quicksand began twenty-eight feet below the ground surface (-3 Cairo datum) and was three feet thick; the second stratum, forty-eight feet below the surface (-23 Cairo datum) and ten feet thick. Coarser sand extended eleven feet below this, from -33 Cairo datum. The second stratum of flowing sand began just below where the lock floor had to be laid. The third layer was 80 feet below the surface (-55 Cairo datum); the tips of the piling would just miss it. Excavation began in November, 1918. While the dredges were at work a wooden sheet piling cofferdam was driven completely around the lock, and about 125 feet from the edge of the bank, to cut off the first quicksand stratum. About 150 feet further in, when the excavation was well advanced, a second ring of sheet piling was driven, to cut off the second stratum, which carried a static pressure of 55 feet and was just a foot or so below where the floor of the lock would be. It was not thought necessary to cut off the third stratum. The excavation was made in the wet. When it was finished the dredges moved back into the Canal, the entrance closed, and the work of unwatering the lock site began. This was in April, 1919. There had never been such a deep cut made in this section. Consequently, the character of the soil, while it could be estimated, could not be known absolutely. And the exact pressure of the gas could not be known. The sands proved to be more liquid and the gas pr
PREV.   NEXT  
|<   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50  
51   52   53   54   55   56   57   >>  



Top keywords:

stratum

 
surface
 

piling

 
excavation
 

dredges

 

character

 
flowing
 

pressure

 

quicksand

 

driven


estimated

 
section
 

November

 

Excavation

 

Consequently

 

proved

 

liquid

 
Coarser
 

extended

 

absolutely


eleven

 

advanced

 

carried

 

thought

 

static

 
finished
 
wooden
 

unwatering

 
closed
 

cofferdam


entrance
 

completely

 

Vicinity

 

sustain

 
enormous
 

weight

 

supply

 

sufficient

 
friction
 

passing


borings

 
calculated
 

sliding

 

engineers

 

Undaunted

 
croakings
 

surrounding

 
subsoil
 

quicksands

 

wouldn