FREE BOOKS

Author's List




PREV.   NEXT  
|<   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  
11 cents. Dredging costs were below the original estimates when labor and supplies were 50 per cent cheaper. The 90,000 cubic yards of concrete in the lock cost an average of $22.50 a cubic yard. This includes cost of material, mixing, building forms, pouring and stripping forms. Mixing and pouring, from the time the material was handled from the storehouse or pile, averaged $1.20 a cubic yard. It would be hard to find cheaper concrete on a work of similar magnitude anywhere, say the engineers. On the siphon the concrete work cost more, because it was a subterranean job, with elaborate shaping. The price there was $35 a cubic yard, in place, including material and form work. To drive the 17,000 bearing piles and 7,000 traveling piles on which the lock is floated, cost an average of 15 cents a running foot. This does not include the cost of the piling. Construction steel cost .12 cents a pound, and erection around 4 cents. These were standard prices. The lock gates, weighing 5,285,000 pounds, cost $845,600, in place. This does not include opening and closing machinery. Three of the bascule bridges crossing the Canal, weighing 1,600,000 pounds each, cost $250,000 each, erected. The fourth bridge, near the lock, weighing 1,000,000 pounds, cost $200,000, erected. This is for superstructure only--it does not include the foundation. The emergency dam bridge, weighing 350,373 pounds, and its 108,256 pounds of turning machinery, cost $96,728, in place. Hoisting machinery cost $40,000 more. The eight girders of the emergency dam, weighing 90 tons each, at $240 a ton, cost $172,800. Machinery for working the ten lock gates, the eight filling gates, and the six capstans--twenty-four 52-horse power electric motors--cost $21,479, f.o.b. New Orleans. The plant for unwatering the lock, consisting of one pump with a capacity of 15,000 gallons a minute, and two with a capacity of 250 gallons each, cost, erected, $11,000. Total mechanical equipment used on the Industrial Canal weighs 14,500 tons. Its cost, including power-house, electrical connections, etc., is $1,516,000. Plant and equipment for building the Canal, including locomotives, cranes, piledrivers, dredges, tools, etc., cost $781,232. Depreciation, up to February, 1921, is set at $266,874, leaving a balance of $514,358, carried as assets. Much of this has already been sold, and more will be disposed of. Following are the firms that executed contra
PREV.   NEXT  
|<   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  



Top keywords:

pounds

 

weighing

 
including
 

machinery

 

erected

 

material

 

include

 
concrete
 

equipment

 

emergency


cheaper

 

pouring

 

building

 
average
 
gallons
 

capacity

 

bridge

 
consisting
 

unwatering

 

Orleans


capstans
 

Machinery

 
working
 

girders

 

filling

 

motors

 

electric

 

twenty

 

carried

 
assets

balance

 

leaving

 

executed

 
contra
 

Following

 
disposed
 
February
 

electrical

 

weighs

 
Industrial

mechanical

 
connections
 
Depreciation
 

dredges

 

locomotives

 

cranes

 

piledrivers

 
minute
 
opening
 

magnitude