FREE BOOKS

Author's List




PREV.   NEXT  
|<   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39  
40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  
or Ransdell of Louisiana in a telegram of congratulation, "and earnestly hope our people will continue to work together with energy and hearty accord until we have gone way over the top in shipbuilding and many other lines." The expression "over the top" had not become the pest that it and other war-time weeds of rhetoric have subsequently proven. That was a time when one could still refer to a "drive" without causing a gnashing of teeth. Picking the site at the Lake Pontchartrain end of the canal, Doullut & Williams Shipbuilding Company began to erect its shipyard. The plant buildings were erected upon tall piling. As the dredges excavated the material from the cut, they deposited it on the site of the shipyard and raised the elevation several feet, so the buildings were only the usual height above the ground. Both sides of the Canal, it should be added, have been similarly raised by excavation material. It was planned that the ships from the Doullut & Williams yard should be sent out into the world through Lake Pontchartrain, which empties into the Gulf of Mexico. There was ample water in the lake, without dredging, to accommodate unloaded ships of this size. But the fact that ships 400 or so feet long and drawing, when loaded to capacity, 27 feet, were to be built at New Orleans, emphasized the belief of those directing the work of the Industrial Canal that the plan on which they were working was too small. An 18-foot canal would not meet the growing needs of New Orleans. Accordingly the Dock Board instructed the engineering department to expand the plans. By June 11, 1918, the plans had been revised to give a 25-foot channel. This would accommodate all but the largest ships that come to New Orleans. The cost of such a lock and canal, George M. Wells estimated, would be $6,000,000, or $2,500,000 more than the estimate for the original canal. The Levee Board promptly raised its ante to $250,000 to guarantee the interest. When the Dock Board floated the first bond issue of $3,500,000 in February, at 95, it reserved the option to issue another $1,000,000 of bonds within thirty days, at the same rate. For $1,500,000 of the new issue, the same syndicate of banks offered 97-1/2, or two and a half points higher than for the first; but for the other million, they held the board to the original rate of 95. President Thompson reported to the Dock Board June 11 that he considered these "very satisfactory terms."
PREV.   NEXT  
|<   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39  
40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56   57   >>  



Top keywords:

Orleans

 

raised

 
buildings
 

shipyard

 

material

 

Williams

 

Pontchartrain

 
Doullut
 

original

 

accommodate


George

 

largest

 

continue

 
estimate
 
people
 

estimated

 

channel

 
instructed
 

engineering

 

department


Accordingly
 

growing

 
expand
 

accord

 

promptly

 

revised

 

hearty

 

energy

 

guarantee

 
points

higher

 

million

 

syndicate

 
offered
 

satisfactory

 
considered
 
President
 

Thompson

 

reported

 
Ransdell

earnestly

 
floated
 
interest
 

February

 

congratulation

 

thirty

 

Louisiana

 
telegram
 
reserved
 

option