FREE BOOKS

Author's List




PREV.   NEXT  
|<   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51  
52   53   54   55   56   57   >>  
essure stronger than anticipated. Quicksands ran through the sheet piling as through a sieve. The walls of the excavation began to slough and cave. The gas pressure became alarming when the weight of earth and water was taken off; sand boils began to develop at the bottom; the floor of the cut was blowing up. The fate of the Industrial Canal hung in the scale. To meet the situation the engineers pumped a great volume of water into the excavation. Its weight counterbalanced the earth pressure of the side and the gas pressure of the bottom. Then another ring of sheet piling was driven inside the other two. This one was of steel, and the walls were braced apart by wooden beams ten inches square and fifteen feet apart in both directions. This is one of the largest cofferdams of steel ever driven. As an added precaution against the danger of a blowout by the third stratum of quicksand, which had a static head of 75 feet, 130 ten-inch artesian wells were driven inside the steel cofferdam. Fifty-six similar wells were driven between the steel and the wooden cofferdams to dry out the second stratum of quicksand, as much as possible, and lessen its flowing character. In November, 1919, the work of unwatering the lock site again began. Only one foot every other day was taken off. Engineers watched every timber. It was not until January 4, 1920, that the unwatering was complete. The plan had worked. Only in one place had there been any movement--a section of the wooden sheet piling about 300 feet long bulged forward a maximum distance of three inches, when the bracing caught and stopped it. Then began the work of driving the 24,000 piles on which the lock was to be floated. They are 60 feet long and their tips are 100 feet below the surface of the ground. In March, 1920, the work of laying the concrete began. The work was done in 15-foot sections, for only a few of the braces could be moved at one time. When it was finished in April, 1921, the lock was in one piece, a solid mass of steel and stone, 1,020 feet long, 150 feet wide, and 68 feet high, weighing, with its gates and machinery, 225,000 tons, and filled with water, 350,000 tons. The concrete floor of the lock is 9 to 12 feet thick, the walls 13 feet wide at the bottom, decreasing to a two foot width at the top. Six thousand tons of reinforcing steel were used in the construction, and 125,000 barrels of cement. There are 90,000 cubic yards of concrete in th
PREV.   NEXT  
|<   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51  
52   53   54   55   56   57   >>  



Top keywords:

driven

 
bottom
 

wooden

 
pressure
 

concrete

 

piling

 
stratum
 

inside

 

cofferdams

 

weight


inches

 
quicksand
 

unwatering

 

excavation

 

ground

 

laying

 

surface

 
driving
 

forward

 

maximum


bulged

 

movement

 

section

 

distance

 

floated

 
stopped
 
bracing
 

caught

 
decreasing
 

filled


thousand
 

reinforcing

 

cement

 

construction

 
barrels
 

machinery

 

finished

 

braces

 
sections
 

weighing


lessen

 
volume
 

counterbalanced

 

pumped

 

situation

 
engineers
 

directions

 
largest
 

fifteen

 

square