: FIG. 70.--"Banjo."]
PIPING.--From the service pipe on which there has been placed a
shut-off, a line of piping, full size, is run through the basement,
overhead to a convenient place, perhaps to a partition in the
center of the cellar. The pipe is brought down and connected into
the end of a header. This header or banjo is made of Ts placed 4
inches center to center. From each T a line of pipe is run to each
isolated fixture or set of fixtures (see Fig. 70). A stop and waste
cock is placed on each line at such a point that all stop cocks
will come in a row near the header. A small pipe is run from the
waste of each stop and discharged into a larger pipe which connects
with a sink. This way of running pipes while it is expensive makes
a very neat and good job. Each stop cock has a tag on it stating
explicitly what it controls. If the building is a large one a
number of these panelled headers are used. A less expensive way to
run this pipe is to branch off from the main at points where the
branch pipe will be as short as possible and use as few fittings
as possible. Stop and waste cocks are then placed on each branch
near the main.
All pipe must follow the direct line of fitting with which it is
connected. The line of pipe should be perfectly straight. If it
seems necessary to bend the pipe to get around an obstacle, then
good judgment has not been used in placing the fitting into which
the pipe is screwed. The fitting should be re-located so that the
pipe can be run without bending. To have true alignment of pipes
the whole job or section of the job must be drawn out on paper
first and any obstacles noted and avoided before the piping is cut.
This not only saves time but it is also the forerunner of a good
job. When getting measurements for piping the same rule or tape
should be used to get out the pipe as was used to get the
measurements.
The water main and branches that run through the basement of a
building are generally hung on the ceiling. Rough hangers of wood,
rope, or wire are usually used to hold the pipe in place at first,
then neat and strong adjustable hangers are placed every 8 feet
apart. There are in use too many kinds of hangers to explain or
describe them here. The essential point of all good hangers is to
have them strong, neat, and so made that perfect alignment of the
pipe can be had. The hangers should be so placed that no strain
will come on the fitting or the valves. A hanger should be pl
|