FREE BOOKS

Author's List




PREV.   NEXT  
|<   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   >>  
It was finally decided to support the tracks on screw-piles carried through the lining of the tunnels, as originally proposed by the writer. In order to know something of the capacity of screw-piles in the actual material to be passed through, it was resolved to test them. A caisson was sunk at the end of one of the Erie Railroad piers on the New Jersey side near the line of the tunnels, and, to obtain parallel conditions as much as possible, the excavation was carried down to the proposed grade of the tunnel. Various types of screw-piles were sunk therein and tests were made, not only of the dead load carrying capacity, but also with the addition of impact, when it was found that screw-piles could be sunk to hard ground and carry the required load. The final part of the test was the loading. The screw-pile, having a shaft 30 in. in diameter and a blade 5 ft. in diameter, was loaded with 600,000 lb., with the result that, for a month--the duration of this loaded test--there was no subsidence. Again, and after the iron tunnel lining had been constructed across the river, tests were made of two types of supports: One a screw-pile 29-1/2 in. in diameter with a blade 4 ft. 8 in. in diameter and the other a wrought-iron pipe 16 in. in external diameter. Tests were made, not only for their carrying capacity, but also for their value as anchorages, and it was found that the screw-pile was more satisfactory in every way; it could be put down much more rapidly, it was more easily maintained in a vertical position, and it could carry satisfactorily any load which could be placed on it as a support for the track. The 16-in. pipe did not prove efficient either as a carrier or as an anchorage. These tests will be mentioned in the detailed description of the work to follow. Figs. 2 and 3 illustrate the general arrangement and details of the machine designed by the writer and used for sinking the test piles in the tunnels. This machine had been used originally on the New Jersey side on the test pile at Pier C, and the adaption was not exactly as shown on these drawings, but if the screw-piles had been placed in the tunnels, the arrangement shown would have been used. Surveys, soundings, and borings were commenced in the latter part of 1901 on an assumed center line of tunnels which was the center line of 32d Street extended westward. The soundings were made from a float stage fastened to a tugboat, the location being determine
PREV.   NEXT  
|<   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

tunnels

 

diameter

 
capacity
 

machine

 

carrying

 

originally

 

proposed

 

lining

 

arrangement

 

support


loaded
 

carried

 

Jersey

 

soundings

 

writer

 

center

 

tunnel

 

determine

 

satisfactory

 

carrier


efficient

 

fastened

 

anchorage

 

easily

 

maintained

 

rapidly

 

westward

 

extended

 

vertical

 
satisfactorily

position

 
Street
 

assumed

 

sinking

 

designed

 

details

 

Surveys

 

drawings

 

borings

 

commenced


adaption

 

description

 

mentioned

 

detailed

 

follow

 

location

 

tugboat

 
general
 

illustrate

 

result