FREE BOOKS

Author's List




PREV.   NEXT  
|<   22   23   24   25   26   27   28   29   30   31   >>  
tunnel, as originally planned, with these pile supports. After the shields had met and the iron lining was joined up, various experiments and tests were made in the tunnel; screw-piles, and 16-in. pipes, previously referred to, were inserted through the bore segments in the bottom of the tunnel, thorough tests with these were made, levels were observed in the tunnels during the construction and placing of the concrete lining, an examination was conducted of the tunnels of the Hudson and Manhattan Railroad Company under traffic, and the result of these examinations was the decision not to install the screw-piles. The tunnels, however, were reinforced longitudinally by twisted steel rods in the invert and roof, and by transverse rods where there was a superincumbent load on the tunnels; it might also be noted that on the New York side, where the tunnels emerge from the rock and pass into the soft material, the metal shell is of cast steel instead of cast iron. Fig. 12 is a typical cross-section of the river tunnels as actually constructed. [Illustration: FIG. 11.--(Full page image) CROSS-SECTION OF TUNNEL SHOWING TRACK SYSTEM AND SCREW-PILE.] [Illustration: FIG. 12.--SUBAQUEOUS TUNNELS CROSS-SECTIONS] During the investigations in the tunnels, borings were made to determine exactly the character of the underlying material, and it was then found that the hard material noted in the preliminary wash-borings was a layer of gravel and boulders overlying the rock. When the borings in the tunnels reached this material it was found to be water-bearing and the head was about equivalent to that of the river. Rock cores were taken from these borings, and the deepest rock was found at about the center of the river at an elevation of 302.6 ft. below mean high water. Rods were then inserted in each bore hole and thereby attached to the rock and used as bench-marks in the tunnels. From these bench-marks, using specially designed instruments, very accurate observations of the behavior of the tunnels could be made, and from these the very interesting phenomenon of the rise and fall of the tunnels with the tide was verified, the tunnels being low at high tide and the average variations being about 0.008 ft. in the average tide of about 4.38 ft.: the tidal oscillations are entirely independent of the weight of the tunnels, since observations show them to have been the same both before and after the concrete lining was in position.
PREV.   NEXT  
|<   22   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

tunnels

 

borings

 
material
 

lining

 

tunnel

 

observations

 

average

 

Illustration

 

inserted

 

concrete


center
 

elevation

 

originally

 

underlying

 

character

 

determine

 

overlying

 

planned

 

equivalent

 

bearing


reached

 

deepest

 

gravel

 

boulders

 

preliminary

 

independent

 

weight

 

oscillations

 

position

 
variations

specially

 
designed
 

attached

 

instruments

 

accurate

 

verified

 

phenomenon

 

behavior

 

interesting

 

SHOWING


examinations

 

decision

 

install

 

result

 

traffic

 

Railroad

 

Company

 
transverse
 

superincumbent

 

invert