FREE BOOKS

Author's List




PREV.   NEXT  
|<   21   22   23   24   25   26   27   28   29   30   31   >>  
he piles and the pier structure with reference to the tunnels. In the tunnels which were constructed in silt farther down the river, by the writer as Chief Engineer for the Hudson Companies, it had been possible to shove the shield through the silt with all the doors closed, displacing the ground and making great speed in construction owing to the absence of all mucking. It was thought that this procedure might be pursued in the larger tunnels of the Pennsylvania Railroad, and it was tried, but it was almost immediately found to be impossible to maintain the required grade without taking a certain quantity of muck into the tunnels through the lower doors, the tendency of the shield being to rise. By taking in about 33% of the excavation displaced by the tunnel, the grade could be maintained. It was considered desirable, owing to this rising of the shields, to increase the weight of the cast-iron lining, and this was done, making the weight of the completed tunnel more nearly equal to the weight of the displaced material. The weight of the cast-iron lining (with bolts) was increased from 9,609 to 12,127 lb. per lin. ft. of tunnel. The weight of the finished tunnel with this heavier iron is 31,469 lb. per lin. ft. The weight of the silt displaced per linear foot of tunnel, at 100 lb. per cu. ft., is 41,548 lb. The weight of the completed tunnel with the maximum train load is 42,869 lb. per lin. ft. The maximum progress at one face in any one month was 545 ft., working three 8-hour shifts, and the average progress in each heading while working three shifts was 18 ft. per 24 hours; while working one shift with the heavier lining referred to above, the delivery of which was slow, the average progress was 11 ft. per 24 hours. [Illustration: FIG. 6.--15' 4" Span Twin Tunnels. Rock Roof.] [Illustration: FIG. 7.--19' 6" Span Twin Tunnels.] [Illustration: FIG. 8.--21' 6" Span Twin Tunnels] [Illustration: FIG. 9.--PROPOSED SHIELD FOR SUBAQUEOUS TUNNELING GENERAL ELEVATION] [Illustration: FIG. 10.--RESTORATION OF PIER 72 (OLD 62) NORTH RIVER TRANSVERSE SECTION AT CENTER OF PIER] In order to permit the screw-piles to be put in place through the lining, cast-steel bore segments were designed, and placed in the invert at 15-ft. centers; these are of such a design as to permit the blade and shaft of the screw-pile to be inserted without removing any portion of the lining. Fig. 11 is a typical cross-section of the river
PREV.   NEXT  
|<   21   22   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

weight

 

tunnel

 

Illustration

 

lining

 
tunnels
 

displaced

 

progress

 

Tunnels

 

working

 

taking


completed

 

making

 

permit

 
shifts
 
maximum
 
average
 

heavier

 

shield

 

heading

 

delivery


referred

 

RESTORATION

 

invert

 
centers
 

designed

 

segments

 
design
 
typical
 

section

 
portion

removing
 

inserted

 
SUBAQUEOUS
 

TUNNELING

 
GENERAL
 

SHIELD

 

PROPOSED

 
ELEVATION
 

TRANSVERSE

 

SECTION


CENTER

 
procedure
 

pursued

 

thought

 
mucking
 

construction

 

absence

 

larger

 
Pennsylvania
 

impossible