FREE BOOKS

Author's List




PREV.   NEXT  
|<   23   24   25   26   27   28   29   30   31   >>  
There was considerable subsidence in the tunnels during construction and lining, amounting to an average of 0.34 ft. between the bulkhead lines. This settlement has been constantly decreasing since construction, and appears to have been due almost entirely to the disturbances of the surrounding materials during construction. The silt weighs about 100 lb. per cu. ft. (this is the average of a number of samples taken through the shield door, and varied from 93 to 109 lb. per cu. ft.), and contains about 38% of water. It was found that whenever this material was disturbed outside the tunnels a displacement of the tunnels followed. The tunnels as above noted have been lined with concrete reinforced with steel rods, and prior to the placing of the concrete the joints were caulked, the bolts grummeted, and the tunnels rendered practically water-tight; the present quantity of water to be disposed of does not exceed 300 gal. per 24 hours in each tunnel 6,100 ft. long. _Bergen Hill Tunnels._--These are two single-track tunnels, 37 ft. from center to center, and extend for a distance of 5,940 ft. from the Weehawken Shaft to the Hackensack Portal. They were built almost entirely through trap rock. The contract was let on March 6th, 1905, to the John Shields Construction Company, but was re-let on January 1st, 1906, to William Bradley, the Shields Company having gone into the hands of a receiver. About 1,369 ft. of the tunnel excavation was done by the Shields Company, but no concrete lining. The maximum monthly progress for all headings was 622 ft., and the average progress was 338 ft. A working shaft 216 ft. deep was sunk from the top of the hill, to facilitate construction. The tunnels are lined with concrete throughout. Typical cross-sections of these tunnels are shown on Plate VIII. In conclusion it may be admissible for the writer after having, in conjunction with Mr. Samuel Rea, experienced the evolution and materialization of this Pennsylvania Railroad scheme, to express his great sorrow for the untimely death of the father of the entire scheme, the late President Cassatt. End of the Project Gutenberg EBook of Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910, by Charles M. Jacobs *** END OF THIS PROJECT GUTENBERG EBOOK SOCIETY OF CIVIL ENGINEERS *** ***** This file should be named 18548.txt or 18548.zip ***** This and all associated files of various formats will be found in:
PREV.   NEXT  
|<   23   24   25   26   27   28   29   30   31   >>  



Top keywords:

tunnels

 

concrete

 

construction

 

Shields

 
average
 

Company

 

scheme

 

tunnel

 

center

 

progress


lining

 

sections

 

conclusion

 
admissible
 
writer
 
Typical
 

monthly

 

conjunction

 

headings

 

maximum


excavation

 

facilitate

 

receiver

 
working
 

father

 

PROJECT

 
GUTENBERG
 
SOCIETY
 

Jacobs

 
LXVIII

Charles
 

ENGINEERS

 
formats
 

Engineers

 
express
 

sorrow

 

untimely

 
Railroad
 

Pennsylvania

 

Samuel


experienced

 
evolution
 

materialization

 

entire

 
Transactions
 

American

 

Society

 

Gutenberg

 
Project
 

President