FREE BOOKS

Author's List




PREV.   NEXT  
|<   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83  
84   85   86   87   88   89   >>  
ng an electrical load at both the maker's works and upon the site of operation. One consideration of importance is worth inquiring into, and this has relation to the largest turbo-generators supplied for power-station and like purposes. Obviously, the testing of, say, a 7000-kilowatt alternator by any standard electrical-testing method must entail considerable expense, if such a test is to be carried out in the maker's works. Nor would this expense be materially decreased by transferring the operations to the power-station, and there erecting the necessary electrical plant for obtaining a water load, or any other installation of sufficient capacity to carry the required load according to the rated full capacity of the machine. Assuming, then, that there exist no permanent facilities at either end, namely the maker's works and the power station, for adequately procuring a steady electrical-testing load of sufficient capacity, there still remains, in this instance, an alternative source of power which is usually sufficiently elastic to serve all purposes, and this is of course the total variable load procurable from the station bus-bars. It is conceivable that one out of a number of machines running in parallel might carry a perfectly steady load, the latter being a fraction of a total varying quantity, leaving the remaining machines to receive and deal with all fluctuations which might occur. Even in the event of there being only two machines, it is possible to maintain the load on one of them comparatively steady, though the percentage variation in load on either side of the normal would in the latter case be greater than in the previous one. This is accomplished by governor regulation after the machines have been paralleled. For example, assuming three turbo-alternators of similar make and capacity to be running in parallel, each machine carrying exactly one-third of the total distributed load, it is fair to regard the governor condition, allowing for slight mechanical disparities of construction, of all three machines as being similar; and even in the case of three machines of different capacity and construction, the governor conditions when the machines are paralleled are more or less relatively and permanently fixed in relation to one another. In other words, while the variation in load on each machine is the same, the relative variation in the governor condition must be constant. By a previously mentioned sys
PREV.   NEXT  
|<   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83  
84   85   86   87   88   89   >>  



Top keywords:

machines

 

capacity

 
governor
 

station

 

electrical

 

testing

 

machine

 
steady
 

variation

 

condition


similar

 

paralleled

 

sufficient

 
expense
 
running
 

relation

 

construction

 
purposes
 

parallel

 

fluctuations


accomplished
 

remaining

 
previous
 

greater

 

receive

 

maintain

 

comparatively

 

percentage

 

normal

 
permanently

conditions

 

previously

 

mentioned

 
constant
 

relative

 
assuming
 
alternators
 

carrying

 

slight

 
mechanical

disparities

 
allowing
 
regard
 

leaving

 

distributed

 

regulation

 

considerable

 
entail
 
method
 

kilowatt