FREE BOOKS

Author's List




PREV.   NEXT  
|<   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84  
85   86   87   88   89   >>  
tem of governor regulation, however, it is possible, considering again for a moment the case of three machines in parallel, by decreasing the sensitiveness of one governor only, to accommodate nearly all the total variation in load by means of the two remaining machines, the unresponsiveness of the one governor to change in speed maintaining the load on that machine fairly constant. By this method, at any rate, the variation in load on any one machine can be minimized down to, say, 3 per cent, either side of the normal full load. There is another and more positive method by which a perfectly steady load can be maintained upon one machine of several running in parallel. This may be carried out as follows: Suppose, in a station having a total capacity of 20,000 kilowatts, there are three machines, two of 6000 kilowatts each, and one of 8000 kilowatts, and it is desired to carry out a steady full-load test upon one of the 6000 kilowatts units. Assuming that the test is to be of six hours' duration, and that the conditions of load fluctuations upon the station are well known, the first step to take is to select a period for the test during which the total load upon all machines is not likely to fall below, say, 8000 kilowatts. The tension upon the governor spring of the turbine to be tested must then be adjusted so that the machine on each peak load is taxed to its utmost normal capacity; and even when the station load falls to its minimum, the load from the particular machine shall not be released sufficiently to allow it to fall below 6000 kilowatts. Under these conditions, then, it may be assumed that although the load on the test machine will vary, it cannot fall below 6000 kilowatts. Therefore, all that remains to be done to insure a perfectly steady load equal to the normal full load of the machine, or 6000 kilowatts, is to fix the main throttle or governing valve in such a position that the steam passing through at constant pressure is just capable of sustaining full speed under the load required. When this method is adopted, it is desirable to fix a simple hight-adjusting and locking mechanism to the governing-valve spindle. The load as read on the indicating wattmeter can then be very accurately varied until correct, and farther varied, if necessary, should any change occur in the general conditions which might either directly or indirectly bring about a change of load. Preparing the Turbine for Testing All
PREV.   NEXT  
|<   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84  
85   86   87   88   89   >>  



Top keywords:

kilowatts

 

machine

 
machines
 

governor

 

station

 

change

 

conditions

 
normal
 

method

 

steady


governing

 

capacity

 

perfectly

 
varied
 
constant
 

parallel

 

variation

 
position
 

released

 

minimum


sufficiently
 

remains

 
Therefore
 

assumed

 

insure

 

throttle

 

farther

 

correct

 

accurately

 
general

Turbine

 

Testing

 

Preparing

 
directly
 

indirectly

 
wattmeter
 
indicating
 

sustaining

 

required

 
capable

passing

 
pressure
 
adopted
 

mechanism

 

spindle

 

locking

 

adjusting

 
desirable
 
simple
 

minimized