FREE BOOKS

Author's List




PREV.   NEXT  
|<   10   11   12   13   14   15   16   17   18   19   20   21   >>  
State of New York organized by the English firm for the purpose of entering into and carrying out this contract. The main features had been agreed upon, and work had begun about two months before. The contract embraced the permanent shafts in Manhattan and Long Island City, the tunnels between these shafts, and their extension eastward in Long Island City to East Avenue, including in all about 23,600 ft. of single-track tunnels. The contract had novel features, and seemed to be peculiarly suitable for the unknown risks and the unusual magnitude of the work. A fixed amount was named as contractor's profit. If the actual cost of the work when completed, including this sum named as contractor's profit, should be less than a certain estimated amount named in the contract, the contractor should have one-half of the saving. If, on the other hand, the actual cost of the completed work, including the fixed sum for contractor's profit, should exceed the estimated cost named in the contract, the contractor should pay one-half the excess and the railroad company the other half; the contractor's liability was limited, however, to the amount named for profit plus $1,000,000; or, in other words, his maximum money loss would be $1,000,000. Any further excess of cost was to be borne wholly by the railroad company. The management of the work, with some unimportant restrictions, was placed with the contractor; the relations of the engineer, as to plans, inspection, etc., were the same as in ordinary work, and the interest of the contractor to reduce cost was the same in kind as in ordinary work. [Illustration: PLATE XIII.--Plan and Profile. East River Tunnels] On account of the extent of the work embraced in this contract, and the dangerous exposure to compressed air required in most of it, it was divided into three residencies; two of these, including also the cross-town tunnels, have been described; the third, with S. H. Woodard, M. Am. Soc. C. E., as Resident Engineer, embraced all tunnels from the easterly end of the work near East Avenue in Long Island City to the meeting points under the river and also the permanent shafts in Long Island City. A few months after the execution of the principal contract, the work to be done was extended eastward 107.5 ft., across East Avenue. The extensions of the tunnels were built without cast-iron linings and with an interior cross-section of the same height as the tube tunnels, but somewhat n
PREV.   NEXT  
|<   10   11   12   13   14   15   16   17   18   19   20   21   >>  



Top keywords:

contractor

 

contract

 
tunnels
 

including

 

Island

 

profit

 

Avenue

 

amount

 

embraced

 

shafts


actual
 

permanent

 

estimated

 

excess

 

eastward

 

ordinary

 

features

 

completed

 

railroad

 

months


company

 

Woodard

 

Profile

 

Tunnels

 

Illustration

 

account

 

extent

 

divided

 

residencies

 
required

dangerous

 
exposure
 

compressed

 

extensions

 

extended

 

linings

 

height

 

interior

 

section

 

principal


Engineer

 

reduce

 

easterly

 

Resident

 

execution

 

meeting

 

points

 
liability
 

single

 

extension