FREE BOOKS

Author's List




PREV.   NEXT  
|<   8   9   10   11   12   13   14   15   16   17   18   19   20   21   >>  
the other hand, as the use of compressed air in building the tunnels was anticipated, an excessive depth below the water surface was to be avoided as far as possible; it was necessary, however, to continue the descending grade some further distance until the tunnels were mostly in rock, so that drainage sumps under the tunnels could be made readily. Eastward from the sumps the tunnels had a rising grade of 0.7% to the established bulkhead line on the Long Island side, giving a cover at the points where the tunnels enter rock, a short distance westward, of about 10 ft. (if the dredging plane should be fixed at some future time at 40 ft. below mean low tide, as may be reasonably anticipated). Eastward from the bulkhead line, Tunnels _A_, _B_, and _D_ have ascending grades of about 1.25%, while Tunnel _C_ rises at the rate of 1.9% in order to effect a crossing over Tunnel _B_ west of the portals. This feature was introduced in order to place the two west-bound tracks together through the Sunnyside Yard, and the heavier grade, being downward with the traffic, was not objectionable. The arrangement of grades and tracks in the approaches and in Sunnyside Yard would require the introduction of too much detail to be taken up here, but will be dealt with in the paper on the Sunnyside Yard. It was recognized from the inception of the project that the tunnels under the East River would be the most difficult and expensive section of the East River Division. The borings had shown a great variety of materials to be passed through, embracing quicksand, coarse sand, gravel, boulders, and bed-rock, as well as some clayey materials. (See Plate XIII.) The rock was usually covered by a few feet of sand, gravel, and boulders intermixed, but, in some places, where the rock surface was at some distance below the tunnel grade, the material met in tunneling was all quicksand; the nearest parallels in work previously done were some of the tunnels under the Thames, particularly the Blackwall tunnel, where open gravel was passed through. Before the plans for the East River tunnels were completed, work had been resumed, after many years' interruption, in the old Hudson River tunnels between 15th Street, Jersey City, and Morton Street, Manhattan, and sand materials were passed through for a short distance. These experiences satisfied nearly all the engineers in any way connected with the work that the shield method was the most suitable for the E
PREV.   NEXT  
|<   8   9   10   11   12   13   14   15   16   17   18   19   20   21   >>  



Top keywords:

tunnels

 

distance

 
Sunnyside
 

passed

 

materials

 

gravel

 

grades

 

bulkhead

 

tunnel

 

quicksand


Tunnel
 

boulders

 

Street

 

anticipated

 

surface

 

tracks

 

Eastward

 

clayey

 

project

 

Division


section

 

borings

 

variety

 

embracing

 

inception

 

coarse

 

difficult

 

expensive

 

recognized

 
previously

Jersey

 
Morton
 

Manhattan

 

Hudson

 

interruption

 

experiences

 

shield

 

method

 

suitable

 

connected


satisfied

 

engineers

 

resumed

 

places

 

material

 

tunneling

 

intermixed

 
covered
 

nearest

 

parallels