FREE BOOKS

Author's List




PREV.   NEXT  
|<   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   >>  
ing on a diagonal, thus making two staves, 3 in. wide at one end and 2-3/4 in. wide at the other. This tapered lagging was used again on the 4-ft. belt and cornice forms, the taper being turned alternately up and down. [Illustration: FIG. 2.--FORMS FOR WATER TOWER VICTORIA, B.C.] The interior diameter being uniform up to the bottom of the dome, collapsible forms were used from the beginning. These forms were constructed in six large sections, 6 ft. high, with one small key section with wedge piece to facilitate stripping, as shown in Fig. 2. There were three tiers of these, bolted end to end horizontally and to each other vertically. Above the taper base and except in the 4-ft. belt and cornice, collapsible forms were used on the outside also. There were six sections extending from column to column and six column sections, all bolted together circumferentially and constructed as shown in Fig. 2. Three tiers of these were also bolted together both vertically and horizontally. Having filled the top tier, the mode of operation was as follows: All horizontal bolts in the lower inside and outside forms were removed, as was also the small key section on the inside; this left each section suspended to the corresponding one immediately above it by the vertical bolts before mentioned. It is thus seen that in each case the center tier performed the double duty of holding the upper tier, which was full of green concrete, and the sections of the lower tier, until they were hoisted up and again placed in position to be filled. These lower forms were then hoisted by hand--four-part tackles being used--and placed in position on the top forms, their bottom edges being carefully set flush with the top edge of the form already in position, and then bolted to it. On the outside, the column forms, and on the inside, the wedge and key sections were set last. A 3-lb. plumb-bob on a fine line was suspended from the inner scaffold and carefully centered over a point set in the rock at the base. This line was in the exact center of the tower, and the tops of all the forms, after each shift, were carefully set from it by measurement, thus keeping the structure plumb. The first 23 in. of the barrel of the tower was moulded with special outside forms, constructed so as to form the bases of the large pilasters. After eleven applications of the 6-ft. forms, these 23-in. sections were reversed to form the capitals, thus making these p
PREV.   NEXT  
|<   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   >>  



Top keywords:
sections
 

bolted

 
column
 

inside

 
section
 
carefully
 
constructed
 

position

 

filled

 

horizontally


vertically

 

suspended

 

cornice

 

center

 

making

 

hoisted

 

collapsible

 

bottom

 

concrete

 

tackles


special

 

moulded

 

barrel

 

structure

 
pilasters
 
capitals
 

reversed

 

applications

 

eleven

 

keeping


measurement

 
scaffold
 
centered
 

diameter

 

uniform

 

interior

 

VICTORIA

 

beginning

 

stripping

 
facilitate

tapered
 
lagging
 

staves

 

diagonal

 
turned
 

alternately

 

Illustration

 

mentioned

 

vertical

 
holding