FREE BOOKS

Author's List




PREV.   NEXT  
|<   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   >>  
ms, scaffolding, etc., were designed by the writer, who was also in immediate charge of the erection. Tenders received for the construction of the tower covered an extremely wide range, and indicated at once the utter lack of knowledge on the part of the bidders of the cost of a structure of this kind. Inasmuch as none of them had had previous experience in this class of construction, the engineer deemed it the part of wisdom and economy to retain the construction under his immediate supervision, and, therefore, the work was done by days' labor. Table 1 gives the cost of the structure. The total herein given will not coincide with the total cost as shown by the city's books, for the reason that various items not properly chargeable to the structure itself have been omitted, the principal ones of which are the cost of the site, the laying of about 600 ft. of sewer pipe to connect with the overflow, and considerable expense incident to the construction of a wagon road to the tower. The rates of wages paid, all being on a basis of an 8-hour day, were as follows: Common labor $2.25 and $2.50 Carpenter 4.00 Carpenter's helper 2.75 Boiler-maker 3.50 Holders on 2.50 Boiler-maker foreman 5.00 Plasterers 6.00 Plasterers' helpers 3.00 The cost of material was as follows: Cement, per barrel $2.53 Sand, per yard 1.47 Rock, per yard 0.80 Lumber, per 1,000 ft. b. m. 14.00 and 16.00 All these prices are for material delivered on the work. An examination of the cost data, as given, will show that for the most part the unit costs are very high. This is due chiefly to the continued interruption of the work, during its later stages, owing to bad weather, particularly in the case of the erection of the steel tank. The material cost in this case was also exceedingly high. In the case of the concreting, inability to purchase a hoist and motor and the high cost of renting the same, together with the delays mentioned, added greatly to the unit cost. When it is considered that the cost of plastering covers that of four coats over the entire inside of the tank and three more over about one-third of it, it does not appear so high, especially in view of the high rate
PREV.   NEXT  
|<   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   >>  



Top keywords:

construction

 

structure

 
material
 

Carpenter

 

Plasterers

 

Boiler

 

erection

 
Lumber
 

delivered

 

inability


prices

 

helpers

 

barrel

 
Cement
 
purchase
 

examination

 

greatly

 
stages
 

covers

 

plastering


considered
 

foreman

 
exceedingly
 

delays

 

mentioned

 

weather

 

inside

 

renting

 

entire

 
interruption

continued

 

chiefly

 

concreting

 
engineer
 

deemed

 
wisdom
 
experience
 

previous

 

Inasmuch

 
economy

retain

 
supervision
 
bidders
 

charge

 

Tenders

 

received

 

writer

 
designed
 
scaffolding
 

covered