FREE BOOKS

Author's List




PREV.   NEXT  
|<   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53  
54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>   >|  
to bring forward material." The above description applies to the later period of construction, when the forces had become thoroughly organized and the work systematized. The following table shows the rate of construction: Ground broken at Omaha December 2nd, 1863. Work commenced at Omaha Spring, 1864. 11 Miles completed to Gilmore September 25th, 1865. 40 Miles completed to Valley December 31st, 1865. 47 Miles completed to Fremont January 24th, 1866. 50 Miles completed March 13th, 1866. 100 Miles completed June 2nd, 1866. 247 Miles completed to the 100th Meridian October 5th, 1866. 305 Miles completed December 31st, 1866. 414 Miles completed to Sidney, Wyo. August, 1867. 516 Miles completed to Cheyenne, Wyo. November 13th, 1867. 573 Miles completed to Laramie, Wyo. May 9th, 1868. 745 Miles completed December 31st, 1868. 1033 Miles completed to Ogden, Utah March 8th, 1869. 1086 Miles completed: To Promontory, Utah April 28th, 1869. Formal connection made May 10, 1869. Regular train service commenced July 15th, 1869. Completed according to Judicial decision November 6th, 1869. The progress made was daily wired East and published in the principal newspapers. Thus in the "Chicago Tribune" items such as "One and nine-tenth miles of track laid yesterday on the Union Pacific Railroad" appeared in every issue. During the construction of the line, headquarters were established at different points at the front, which were used as a basis of operations for the construction of the section beyond. These places enjoyed a temporary boom, some of them like Jonah's Gourd to wither up and die away, others profiting by the start are today points of importance. The first of these was North Platte, Nebraska, its selection being caused by the delay incident to bridging the river. This was the terminus of the road during the fall of 1866 and up to June 1867. During this time it was the distributing point for all the country west. The mixture of railroad laborers, freighters, etc., all of them with more or less money, inaugurated a rough time and was the beginning of the wild scenes that attended the construction
PREV.   NEXT  
|<   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53  
54   55   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   >>   >|  



Top keywords:

completed

 

construction

 
December
 

November

 

commenced

 

points

 

During

 

appeared

 

wither

 

Pacific


yesterday
 
Railroad
 
places
 

section

 

established

 

headquarters

 
enjoyed
 

temporary

 

operations

 

Platte


railroad
 

laborers

 

freighters

 

mixture

 

distributing

 

country

 

scenes

 

attended

 

beginning

 

inaugurated


Nebraska
 

importance

 

profiting

 

selection

 

terminus

 

bridging

 

caused

 

incident

 

Valley

 

September


Gilmore
 

Spring

 

Fremont

 

January

 

Meridian

 
October
 

broken

 

period

 

forces

 

applies